3. Site 7351

Shipboard Scientific Party2

OPERATIONS SUMMARY

Overview and Significant Accomplishments

We began Leg 176 with the first line ashore in Cape Town, South Africa, at 1000 hr on 8 October 1997. Time as reported in this summary is local ship time (Universal Time Coordinated [UTC] + 2 hr). Leg 176 drilling operations were quite different from those of most Ocean Drilling Program (ODP) legs. We conducted all drilling operations at a single site in a single hole. Hole 735B was first established during Leg 118. During that leg, a hard-rock base (HRB; Fig. F1) was set in 731 m of water and a 97_8.gif (82 bytes)-in hole was cored to a depth of 500 meters below seafloor (mbsf). Another 0.7 m of penetration was made on that leg using the 33_4.gif (83 bytes)-in Navidrill Core Barrel, establishing a "cored" total depth of 500.7 mbsf. During Leg 176 we set out to reoccupy Hole 735B and deepen it to a depth of at least 1500 mbsf. We were overwhelmingly successful in meeting this objective, deepening Hole 735B from 1235.8 meters below rig floor (mbrf), or 504.8 mbsf, to 2239.0 mbrf, or 1508.0 mbsf. We have not established why our Leg 176 beginning sub-bottom bottom depth was 4.8 m deeper than the total depth documented at the end of Leg 118.

We used the rotary core barrel (RCB) wireline coring system exclusively during the leg. Ten RCB C-7 core bits yielded the recovery of 122 cores. A total of 1003.2 m of new hole was cored, from which 865.99 m of core was recovered, or 86.3% of the section (Table T1). Penetration rates varied from 1.3 to 6.1 m/hr in the gabbro and olivine gabbro. We achieved faster rates in coarser grained olivine gabbros and in fractured rock. Drilling rates were slower in more massive, finer grained, or strongly foliated rocks. Conversely, recovery rates were high, close to 100%, in both massive and fine-grained gabbro, but were much lower in highly fractured rock. The average rate of penetration (ROP) for the leg was 2.7 m/hr. We took drift measurements at eight stations between 500 and 1400 mbsf. Hole deviation based on the Tensor electronic multishot data was moderate, varying between 4.3º and 4.8º.

Our progress in the hole ended when a 5-in drill pipe connection failed, leaving 131 joints of 5-in drill pipe and a coring bottom-hole assembly (BHA) in the hole, a total of 1403 m of drill string. The failure occurred when the pipe was 97 m off bottom during a routine wiper trip to replace wear-knotted drill pipe with standard 51_2.gif (82 bytes)-in drill pipe. At the time of the failure, as during most of our operations during this leg, we were experiencing heave of the rig floor in excess of 2 m. On more than one occasion, including this episode, the pipe caught on a ledge in the borehole and lifted out of the elevator at the rig floor. We attempted to fish the severed pipe using a 91_2.gif (82 bytes)-in overshot dressed with a 67_8.gif (82 bytes)-in basket grapple and mill control. We successfully engaged the pipe and as it was being lifted to its total weight of 130,000 lb the drill string parted again. The new failure point coincided with a point at which the pipe had apparently buckled upon impact with the bottom of the hole. We ultimately recovered a total of 497 m of 5-in drill pipe. The fish remaining in the hole (906 m) consists of 26 stands of 5-in drill pipe (734 m) plus the coring BHA (172 m). We made seven unsuccessful fishing attempts over a period of 7.4 days before abandoning attempts to clear the hole.

Besides the drill string, several historical records were also broken during Leg 176. More hard rock (866 m) was recovered during Leg 176 than during any other leg in the history of ODP or the predecessor Deep Sea Drilling Project (DSDP), nearly doubling the previous record, also made in Hole 735B during Leg 118, of 434 m. We also cored more than twice the hard rock (1003 m) of any other single leg, shattering the previous Leg 118 record of 501 m. Hole 735B is the fifth deepest hole in ODP history. In addition, Leg 176 coring in Hole 735B now qualifies as the third longest single-hole continuously cored interval (mud or rock) in ODP history.

We conducted logging operations in two phases. The first phase (two logging runs to 492 mbsf) was done after the initial reentry into the hole and before commencing coring operations. It included the Triple-Combo (natural gamma sonde [NGS], accelerator porosity sonde [APS], hostile environment lithodensity sonde [HLDS], and the dual laterolog [DLL]) plus temperature log. The second string included the NGS, the dipole shear sonic imager (DSI), and the Formation MicroScanner (FMS). We ended this logging run early, however, because of apparent data acquisition difficulties.

We conducted the second phase of logging and vertical seismic profile (VSP) experiments near the end of the leg, after several attempts to recover the lost drill string. The first tool string consisted of the HLDS, caliper, APS, and the hostile environment spectral natural gamma sonde (HNGS). The second logging run consisted of the natural gamma tool (NGT), DSI, General Purpose Inclinometry Tool (GPIT), and the FMS probes. The third tool string was composed of the NGT, GPIT, and DLL probes.

During the first logging run on phase II, we obtained good density, porosity, and gamma-ray measurements from 49 to 595 mbsf, or 11 m above the hole obstruction (606 mbsf). The second logging run (DSI-FMS) resulted in good data recorded by the DSI. Cross-dipole and P- and S-wave mode data were recorded during the first pass, and cross-dipole, upper dipole, and Stoneley modes during the second pass. The FMS, however, did not fare as well. After spending some time testing different gain options to improve the data quality from the FMS, we opted to recover the tool and repeat the logging run with a replacement FMS. Unfortunately, the results of the second tool run were similar to those of the first. Shore processing later showed that the tools could not respond quickly enough to the extreme resistivity contrasts between lithology types. The deployment of the third tool string resulted in very good resistivity data with the DLL.

The fourth and final logging run consisted of the Schlumberger three-component VSP tool. The objectives of the VSP were to acquire data over the section of hole not covered by the Leg 118 VSP and to acquire better VSP data using the new tool. We hoped that new data would resolve sub-bottom reflectors below 1500 mbsf and give better observations of the seismic attenuation at the site. The VSP operation took about 16 hr rig floor to rig floor. We shot both air gun and water gun sources with the sonde clamped at 23 depths in the hole. The tool did not give appreciably better data than were acquired on Leg 118, but we did fill in the coverage between 500 and 600 mbsf.

After concluding the wireline logging and VSP runs we round-tripped the drill string one last time for a final fishing attempt. The fish was contacted ~2 m deeper than before at 1339 mbrf, or 608 mbsf. During subsequent working of the pipe, we contacted the fish at the shallower (606 mbsf) depth; however, all attempts at engagement proved futile. We abandoned our final fishing attempt at 1400 hr on 1 December 1997 and prepared to get under way for Cape Town, South Africa. We departed Hole 735B at 1900 hr on 1 December 1997.

Operations Narrative

Transit to Site 735

At 1300 hr on 15 October 1997, we passed the last line ashore and headed out of Table Bay, Cape Town harbor. At 1346 hr we discharged the pilot and got under way at full speed for Site 735. Rough seas rounding the Cape of Good Hope, strong headwinds, and the effects of the Agulhas Current slowed our transit; however, we ultimately accomplished the 2003-nmi transit to Site 735 in 9.0 days at an average speed of 9.3 kt. Propulsion motor P-17A was taken off-line during the transit due to armature damage when a field coil failed. The engineers rebuilt the assembly while on site, and it was placed back on line before our departure for Cape Town. We were also forced to reduce speed for ~1 hr using manual steering and magnetic compass for heading when an emergency generator test caused a malfunction of the automatic station keeping (ASK) system. This system is linked to the ship's gyrocompass. The problem was ultimately traced to a dead cell in the ASK back-up battery bank. Subsequent system testing was successful once the bad battery was replaced. Besides routine preventive-maintenance system (PMS) tasks, the installation of a rig-floor waste-collection system was completed during the transit and efforts continued on the installation/testing of a new waste-burning incinerator system for future Antarctic expeditions. We arrived on location 24 October 1997, and at 1345 hr the first positioning beacon was dropped using the 10-yr-old Satellite Navigation coordinates (32º43.395'S, 57º15.959'E) for Hole 735B.

Site 735

Locating Hole 735B

We immediately went to work making up an outer core barrel assembly and four stands of 81_4.gif (82 bytes)-in drill collars. Three stands were temporarily stored in the derrick because our first pipe trip used only a single stand of drill collars in the BHA for logging the existing 500-m-deep hole. After tripping the drill string to the seafloor, we deployed the vibration-isolated television camera and began searching for Hole 735B. Because this hole was being reoccupied, and the seafloor depth was known to be 731.0 m, we did not require a precision depth recorder reading. In >1 hr, using an expanding-box search pattern, we located the HRB deployed during Leg 118. Final GPS location coordinates for Hole 735B were ultimately determined to be 32º43.3928'S and 57º15.9606'E, or ~5 m away from the original coordinates of 10 yr prior.

Initial Logging of Hole 735B

At 2000 hr on 24 October 97, we reentered Hole 735B; however, resistance was encountered almost immediately at a depth of 736 m (5 mbsf). We pulled clear of the seafloor, picked up the top drive, and using slow rotation reentered for the second time at 2130 hr. This time the end of the drill string was placed at a logging depth of 780 m (49 mbsf) without incident.

Logging operations began with the Triple-Combo consisting of natural gamma, porosity, lithodensity, and temperature tools. We also obtained temperature data using the Lamont-Doherty Earth Observatory temperature tool. The first logging run advanced to 492 mbsf, or just 8 m short of the total depth of 500.7 mbsf. Our second logging run included the NGS, the DSI, and the FMS. We had to end this run early because of data acquisition difficulties. We completed the first phase of logging operations by 1700 hr on 25 October 1997.

Following a pipe trip to change over to a coring BHA, we again reentered Hole 735B and ran to bottom. The top drive was used at several points to rotate past obstructions; however, minimal resistance was encountered on the trip. Because the last core recovered during Leg 118 was taken with the Motor-Driven Core Barrel (MDCB), we expected the lowermost 0.7 m of the hole would be under gauge for RCB operations. The bit tagged bottom at 504.8 mbsf, or 4.8 m below the depth that RCB coring ended on Leg 118, and 4.1 m below the depth of MDCB drilling. The discrepancy between the depth to the bottom of the hole recorded at the end of Leg 118 and the depth at which Leg 176 coring operations began remains unexplained.

Core Bit 1

We began continuous coring operations with Core 176-735B-89R at a total depth of 1235.8 m, or 504.8 mbsf. For BHA configurations, bit type, drill-string configurations, and bit-specific recovery for all bit trips, the interested reader is referred to Table T2.

Partial cores (ranging in length from 3.7 to 8.0 m) were taken beginning with Core 176-735B-92R because of the extremely slow ROP. Core jamming inside the acetate butyrate core liners occurred on three cores in a row, so, beginning with Core 176-735B-96R, we deployed the core barrels without liners. We used bentonite gel mud exclusively during Leg 176, circulating the mud in 20-bbl sweeps every other core to enhance hole cleaning. Upon recovering Core 176-735B-96R, we found that the core catchers and cored material were missing. The threaded connection between the core catcher sub and the 111_8.gif (82 bytes)-in inner barrel sub unscrewed, leaving the core barrel components and core material inside the pipe just above the bit. We decided that attempting to fish the items out of the pipe would be futile; therefore, the bit run was ended at a depth of 556.3 mbsf. The bit cleared the rig floor at 2145 hr, and Core 176-735B-96R was recovered from the pipe. We found the core bit to be in good condition except for the inner (nose) row of carbide buttons.

Core Bit 2

Using the same BHA configuration we deployed the subsea television camera and reentered the HRB in less than 15 min of ship maneuvering. These quick (15 min) reentries proved to be the rule for the remainder of the leg. In this case, the driller again could not induce the bit into the hole, and another reentry had to be made with the top drive picked up. On the second attempt we reentered the HRB at 0300 hr on 28 October 1997 and, using slow top-drive rotation, walked the bit into the off-center hole (Fig. F1) without incident. Continuous coring began with Core 176-735B-97R from 556.3 mbsf. Coring on this bit run was affected by large long-period swells, which translated into rig floor heaves of 2.0 to 3.0 m, making it difficult for the driller to maintain optimum weight on bit (WOB). The seas moderated on the third day, but by then it was time to pull the bit for replacement. Our original goal was to obtain a minimum of 40 rotating hours on this bit, but because of the large load fluctuations, we decided to be conservative and terminate coring operations slightly earlier than planned. In addition, the driller noted elevated pump pressure during the final three cores, and we suspected that two of the bit jets may have become plugged. We suspended coring after cutting Core 176-735B-111R to a depth of 642.7 mbsf. The bit cleared the rig floor at 0930 hr on 30 October 1997. The core bit was in good condition except for the inner (nose) row of carbide buttons. The bit did have two jets plugged with a combination of cuttings and Teflon bit-seal material. In addition, a 5-in-long crack extended longitudinally outward from the base of the pocket in the drilling-jar body.

Core Bit 3

After reentry with this bit run, we encountered 8 m of loose fill at the bottom of the hole. We initiated continuous coring with Core 176-735B-112R at 642.7 mbsf. Our goal on this run was to replace the bit after completing Core 176-735B-124R; however, observations of core tapering and some suspicious markings in Core 176-735B-123R persuaded us to halt operations with only 3.4 m of advance on Core 176-735B-124R. The bit cleared the rig floor at 0530 hr on 2 November 1997. Surprisingly, we again found the bit to be generally in good condition with effective bearing seals and no sign of imminent catastrophic failure. The internal cutter wear was more advanced than on the two earlier bits with the inner (nose) row of carbide buttons completely worn back into the matrix material. One of the two opposite cutters with three carbide inserts was also worn back to the matrix material. In addition, there was some wear at the tip of the core guide, indicating that ROP would have soon begun to suffer.

Core Bit 4

As a precaution, because of the earlier cracking incident, we again laid out the drilling jars for nondestructive testing (NDT) inspection and pressure testing prior to running them back in the hole with the fourth core bit. During the NDT inspection, we identified small cracks initiating from the two corners at the base of each pocket in the jar body. We set these jars aside, and because the remaining set of drilling jars had not yet passed pressure testing, this BHA was made up without jars. At 0845 hr on 2 November 1997, we reentered the hole and ran to 742.0 mbsf, or ~10 m off bottom. Using the Tensor electronic multishot tool we conducted a wireline drift survey from 742.0 to 500.0 mbsf. Six measurements made at 50-m increments indicated a hole deviation of 4.5º ± 0.3º. Upon completing the survey, we began continuous coring with Core 176-735B-125R from 752.1 mbsf. While cutting Core 176-735B-136R, circulating pressure dropped by 100 psi, and we assumed that the RCB bit seal had failed. Although the bit continued to recover gauge core and advance at a respectable rate, we decided again to be conservative and pulled the bit after 46.8 hr. We halted coring after recovering Core 176-735B-140R to 889.3 mbsf. The bit arrived at the rig floor by 0500 hr on 5 November 1997. Once again, the bit was in good condition with no sign of imminent catastrophic failure. As expected, the internal cutter wear was slightly more advanced than on previous bits. The inner (nose) row of carbide buttons was completely worn back into the matrix material, and both of the two opposite cutters with three carbide inserts each were also worn back to the matrix material. There was slight wear at the tip of the core guide. The bearing seals were still effective, and the bearing condition was actually slightly better (tighter) than that of the previous bit.

Core Bit 5-First Deployment

During the previous bit run we rebuilt the final remaining set of drilling jars and added packing to the seal chamber. The jars passed a pressure test of 1500 psi for 10 min and were judged acceptable for use. A new C-7 core bit was made up, and after 15 min we made yet another routine reentry at 0800 hr on 5 November 1997. We were tripping the bit to bottom when it encountered a hard bridge at a depth of 123 mbsf. After picking up the top drive we again encountered an obstruction, this time at 117.0 mbsf. We spent close to 11_2.gif (82 bytes) hr attempting to clear the bridge with the C-7 core bit to no avail. The top drive repeatedly stalled out with little or no WOB each time it contacted the obstruction. After deliberation, we decided that a better strategy would be to use a more robust tricone drill bit to clear the hole. The drill string was tripped back to the rig floor by 1545 hr that same day.

Tricone Drill Bit

Leaving the BHA configuration unchanged, we exchanged the Rock Bit Industries C-7-style core bit for a Smith F57 tricone drill bit. We reentered the hole at 1915 hr on 5 November 1997 (15-min reentry), and the pipe tagged the obstruction at the same depth as before (117.0 mbsf). Top-drive stalling continued to be a problem during our attempts to clear the bridge. This was aggravated by significant heave resulting from long-period swells generated by a significant low-pressure cell some 50 miles to the south of the drilling location. Ultimately, by using high rotation speeds (100-130 rpm) coupled with low WOB and some skillful drilling supervised by the Overseas Drilling Limited (ODL) drilling superintendent, we cleared the bridge in the hole. There were, however, top-drive stalling torques of 750 A and overpulls of up to 60,000 lb during the episode. We theorized that an angular piece of material must have sloughed off of the side of the hole, leaving a high angle bridge that caused both core and drill bits to wedge immediately upon contact. We subsequently washed/reamed the hole to bottom to ensure that any other bridges or hard fill on bottom would be broken up by the more rugged tricone drill bit before resuming coring operations. No other bridges were identified, however, and only 2.0 m of soft fill was encountered on bottom. We circulated this out in short order and pumped a 50-bbl bentonite gel mud sweep. We then tripped the pipe back to return the BHA to a coring configuration. The tricone drill bit cleared the rig floor at 0630 hr on 6 November 1997.

Core Bit 5-Second Deployment

As the bit used in our fifth deployment showed no signs of wear, we ran the same bit back into the hole following hole-cleaning operations. The drilling jars failed a routine pressure test. Because they were the only remaining set of jars, we delayed reentry until the packing on the jars could be replaced and pressure tested. We then made up the jars with the remaining BHA and tripped the drill string to bottom. The hole was reentered at 1230 hr on 6 November 97 after another routine 15-min ship maneuver. We encountered no ledges, and the pipe went straight to bottom without incident. No fill was detected at total depth, and we began continuous coring with Core 176-735B-141R from 889.3 mbsf. While we were cutting the second core of this bit run, the drilling torque escalated to 600 A and we experienced 60,000 lb of overpull picking up off bottom. High torque, top-drive stalling, and overpull of 40,000-60,000 lb continued through Core 176-735B-145R, but we encountered no problems after Core 176-735B-146R. We halted coring while cutting Core 176-735B-151R at a depth of 987.5 mbsf when drilling torque escalated to 40-50 or more amps from the normal and ROP dropped off to 1.6 m/hr. The bit cleared the seafloor at 0250 hr and was at the rig floor by 0415 hr on 9 November 1997. As before, we found the bit to be in good condition with no sign of imminent catastrophic failure. The internal cutter was again severely worn, with the inner (nose) row of carbide buttons completely worn back into the matrix material. Both of the two opposite cutters with three carbide inserts were also worn back to the matrix material. Bearing seals were effective, and the bearing condition was good.

Core Bit 6

We made up yet another new C-7 core bit with the BHA. However, drilling jars were not included on this run because the final remaining set also showed evidence of cracking during NDT inspection. After reentry at 0700 hr on 9 November 1997, the drill string was run to the bottom without incident. We initiated continuous RCB coring on Core 176-735B-152R at a depth of 987.5 mbsf and continued coring through Core 176-735B-163R to a depth of 1099.4 mbsf. We terminated coring early while cutting Core 176-735B-163R because the drilling torque abruptly increased 40-50 or more amps and the ROP dropped to 2.5 m/hr from earlier, higher rates. The bit reached the rig floor by 2330 hr on 11 November 1997 and again was in good condition with no sign of imminent catastrophic failure. The internal cutter wear was severe, however, and the inner (nose) row of carbide buttons was completely worn back into the matrix material, as were both of the two opposite cutters with three carbide inserts. One insert had fallen out of the core-gauge row and another had broken off. Bearing seals were effective, and bearing condition was as good as, or better than, on any of the previous bits.

Core Bit 7

We made up the seventh new C-7 core bit and welded closed a crack in the latch sleeve before running in the hole. The BHA was run in the hole as before without drilling jars. We reentered at 0245 hr on 12 November 97 and ran the drill string to bottom without incident. We initiated continuous RCB coring with Core 176-735B-164R at a depth of 1099.4 mbsf and continued to a depth of 1191.1 mbsf. No fill was identified after any of the connections. However, while cutting Core 176-735B-174R, the drilling torque increased dramatically from the normal 360-400 A to 500-600 A. The torque dropped back to normal when we picked the bit up off bottom. We had only 33.3 rotating hours on the bit; nevertheless, we could not rule out the possibility of a pending bit problem. We therefore decided to err on the side of conservatism and brought back the final core after advancing only 3.0 m. Upon clearing the rig floor at 0430 hr on 14 November 1997, we found the bit to be in excellent condition; similar to the bit used during the second core-bit run of 36.0 hr. There was, instead, a high degree of wear and burnishing on the crossover sub between the 5-in and 5½-in drill pipe during the pipe trip. A check of the pipe tally placed the crossover at or near seafloor in the vicinity of the HRB when the bit was on bottom. This may have been the source of the excessive drilling torque.

Core Bit 8

We ran the eighth new C-7 core bit in the hole and replaced the crossover sub between the 5-in and 51_2.gif (82 bytes)-in drill pipe during the pipe trip. In addition, we added 10 more stands of 5-in drill pipe to the string to remove the crossover from the area of the HRB. The bit went to the bottom of the hole without incident after another routine 15-min reentry (0700 hr on 14 November 97). We began continuous RCB coring with Core 176-735B-175R at a depth of 1191.1 mbsf and continued to a depth of 1360.6 mbsf. Coring was terminated after advancing 5.6 m on Core 176-735B-193R when the drilling torque increased by 50-100 A. The bit had 53.8 rotating hours at that time so we conservatively pulled the bit. The bit reached the rig floor at 1530 hr on 17 November 1997 and was in good condition. One cover plate from the grease reservoir was missing, however, and this may have contributed to the increased torque downhole.

Core Bit 9

On our ninth bit run, we used another new C-7 core bit with an additional five stands of 5-in drill pipe to keep the 5-in × 51_2.gif (82 bytes)-in crossover sub well above the HRB. After slipping and cutting the drill line for the first time this leg, we reentered the hole at 2045 hr on 17 November 1997 and ran to a depth of 1295.0 mbsf, where the bit met an obstruction and was unable to pass. We picked up the top drive and were able to ream the remaining 65.6 m without difficulty. We found no indication of any fill on bottom, and the drilling torque was normal. Continuous RCB coring was initiated with Core 176-735B-194R at a depth of 1360.6 mbsf and continued to a depth of 1386.4 mbsf. We stopped coring 3.1 m into Core 176-735B-197R because of worsening weather. In addition to the heave compensator beginning to exceed operating limits, we experienced five 3% and two 5% positioning alarms. We stopped coring after only 8.8 rotating hours on the bit and began to pull out of the hole. After pulling the pipe to a depth of 739.0 m (8.0 mbsf), the drill string was hung off on the elevators while the driller laid out the previously pulled stand of drill pipe. At that time the bit contacted a ledge in the hole, causing the drill string to jump upward in the landing elevators. Using the stand in the string above the rotary, the string was lifted ~2.0 m off the elevators until the bit was free from the ledge. Two attempts were then required before the drill string could be lowered past the ledge to the next tool joint. The bit cleared the seafloor at 2115 hr on 18 November 1997 with marginal weather and sea conditions. Winds were ranging from 33 to 41 kt gusting to 51 kt, and swells were running 8-18 ft at 8- to 9-s periods. The vessel was heaving 10-18 ft. Because of extremely rough seas at the time, we decided to hang off the BHA/transition pipe below the keel and wait for the weather to abate. At 2215 hr on 18 November 1997, the string was hung off on the elevators, and we commenced "waiting on weather." By 0245 hr the following morning, conditions moderated sufficiently to recover and conduct a NDT of the BHA. We found no cracks during the "magnaflux" inspection; however, two drill collars (2 and 3) were bent. This was obviously the result of the incident just described. The recovered bit was in excellent condition although (nose) cutter wear was much higher (50% of the carbide inserts worn away) than expected of a bit with less than 9 rotating hours.

Core Bit 10

By 1500 hr on 19 November 1997 our sea conditions had moderated, and the captain felt confident that the storm system was both weakening and moving away. We made up another new C-7 core bit, ran in the hole, and reentered at 1945 hr on 19 November 1997. When the bit reached a depth of 1295.0 mbsf it was again unable to pass, just as in the eighth bit run. As before, we picked up the top drive and reamed to bottom without incident. We proceeded to rotary core with Core 176-735B-198R at a depth of 1386.4 mbsf and continued to a depth of 1508.0 mbsf. We took drift measurements at 1100 and 1400 mbsf and determined hole deviation at those points to be 4.6º and 4.8º, respectively.

We interrupted coring after Core 176-735B-210R to short trip five stands of wear-knotted drill pipe out of the hole and replace it with standard 51_2.gif (82 bytes)-in drill pipe. We could have continued coring using knobby drilling joints, but the cores would have been shorter (9.2 m vs. 9.6/9.7 m) and the knobbies would have been more time-consuming to handle, whereas the wear-knotted pipe could be handled using the automated pipe racker. After pulling all but four joints of the wear-knotted pipe from the hole, we suffered a drill-string failure. The pipe was landed in the elevators while the driller placed a double joint of drill pipe into the mousehole with the top drive. During this time the drill string twice came into contact with a ledge in the hole when the vessel heaved down, causing the string to rise ~0.5 m above the landing elevators. The driller moved as quickly as possible to reinstall the top drive, and the string was lifted off of the landing elevators. However, by that time the damage had been done; the weight indicator showed a loss of 130,000 lb of string weight.

Our calculations indicated that the string parted in the 5-in drill pipe at or near the seafloor. We sent down the subsea camera to inspect the drill string/HRB, confirming that the failed pipe was not above the seafloor, and then recovered the drill string. At 0600 hr on 22 November 1997, we identified the point of failure as the last-engaged thread of a 5-in drill-pipe pin connection located at 739 m (8 mbsf). The fish we left in the hole was 1403 m in length and consisted of a 172-m-long BHA plus 432_3.gif (84 bytes) stands of 5-in drill pipe (1231 m).

Fishing Attempts

We made a total of eight attempts to fish the drill string from the hole. Interspersed with the fishing attempts were several pipe trips with milling tools and one for logging operations. During the first fishing attempt, we were able to latch onto the severed drill string. We were lifting it to its total weight of 130,000 lb when it parted once again, leaving only 35,000 lb of weight suspended below the overshot tool. We pulled the fishing string to the surface and recovered a total of 497 m of 5-in drill pipe by 1930 hr on 22 November 1997. The drill string had parted in the 5-in drill pipe tube 2 ft below a box tool joint. This was at a point where the tube had buckled when the string impacted the bottom of the hole after the initial failure. The portion of drill string remaining in the hole (906 m) consisted of 26 stands (734 m) of 5-in drill pipe plus the coring BHA of 172 m.

During subsequent fishing/milling trips, we repeatedly encountered difficulties with ledges near the top of the hole. Although we tried several different fishing and milling tools, many fabricated on site by the ODL crew, none of these was successful in engaging the severed drill string (for a complete list of fishing and milling drill string configurations, see Table T2). A common result of milling operations was advancement of the drill pipe beyond the depth where the top of the severed drill string was initially encountered. Subsequent fishing attempts, however, routinely stopped at the original depth of the top of the severed pipe, indicating that the mills were side-tracking along the drill string rather than grinding away the top of it.

On our third milling attempt, we inserted a drill string stabilizer into the BHA to help keep the mill straight and potentially reduce side-tracking. Unfortunately, unacceptably high torque immediately after reentry indicated that the upper part of the hole was too narrow for such a configuration, and the stabilizer was removed from the milling BHA. Our fourth and final milling attempt went much better than previous attempts, with constant torque and a very slow ROP. On recovery of the milling tool, we noted a concentric wear pattern with a 5-in diameter in the center of the mill face. We were encouraged enough by this evidence to plan a final fishing trip, after allowing time for our logging program.

Wireline Logging and VSP Experiment

We used a shortened BHA for logging and installed a landing saver sub with a "special" landing ring two drill collars up from the bit to provide a landing point for the Kinley Crimper/Cutter assembly, should it be required. The landing ring inside diameter had to be opened up to 3.918 in to accommodate the oversized Schlumberger VSP tool. We reentered the hole at 0745 hr on 29 November 1997, and the pipe was placed at 780 mbrf, or 49 mbsf, with a 30-ft drilling knobby through the guide horn. At 0915 hr we began to rig up the Schlumberger logging sheaves and wireline compensator.

The first tool string consisted of the high-temperature lithodensity tool (HLDT), caliper, APS, and HNGS probes. The second logging run consisted of NGT, DSI, GPIT, and FMS probes. The third tool string was composed of NGT, GPIT, and DLL probes. The fourth and final run consisted of the Schlumberger BGKT three-component VSP tool. During the experiment, a hydrophone that had been hung off the rear port side crane to monitor noise in the water column failed. To avoid tangling the cable in the main screws, we brought the hydrophone back on deck for the remainder of the experiment. We rigged down the VSP tools and logging sheaves by 0415 hr on 1 December 1997 and proceeded to pull the drill string, clearing the seafloor at 0430 hr and reaching the rig floor by 0530 hr.

Final Fishing Attempt

While the logging/VSP efforts were under way, we fabricated another modified fishing assembly. An overshot assembly was shortened as much as possible, bringing the mill control and basket grapple closer to the open end of the overshot. In addition, "Cutrite" hard facing was applied to the lip guide, creating a "milling-capable" overshot assembly. We hoped that the combination of the shorter fishing assembly and the limited milling ability would allow the basket grapple to engage the drill pipe. We encountered the top of the severed drill string ~2 m deeper than before at 1339 mbrf, or 608 mbsf. During subsequent attempts to grasp the pipe, however, we made contact at the shallower (607 mbsf) depth. To our dismay, even after several hours and a herculean effort by the drilling crew, we were not able to extract the drill string from Hole 735B. We abandoned our final fishing attempt at 1400 hr on 1 December 1997 and prepared to get under way for Cape Town, South Africa. When the fishing tool was recovered, it showed obvious indications that something had at some time been inside the overshot as far as the mill control assembly.

Transit to Cape Town, South Africa

We began the return voyage to Cape Town, at 1900 hr on 1 December 1997. During the transit, the rig crews worked on the usual cleanup, painting, report writing, and PMS activities. In addition we held a meeting with rig personnel and the Leg 176 co-chief scientists/staff scientist to discuss approaches and operational options for a possible future deep hole (2500+ mbsf) in the Hole 735B Southwest Indian Ridge operating area.

We arrived at the pilot station at 1030 hr 9 December 1997 after a 1998-nmi voyage that averaged 10.9 kt. The first line was ashore at 1130 hr on 9 December 1997, officially ending Leg 176.

1Examples of how to reference the whole or part of this volume can be found under "Citations" in the preliminary pages of the volume.
2Shipboard Scientific Party addresses can be found under "Leg 177 Participants" in the preliminary pages of the volume.

Ms 176IR-103