Date (January 1999) |
Time (UTC) | Logging operations |
---|---|---|
20
|
0200
|
Hole preparation complete. Rig up wireline. |
|
0355
|
Rig into hole with NGT-DSI-DITE(+TAP). |
|
0505
|
Bridge at 593 mbsf prevents going down to bottom of hole. Start logging upward at 900 ft/hr. No response from any of the tools. Pull out of hole. |
|
0640
|
Tool back on the rig floor. Check for tool failure. |
|
0815
|
DSI is replaced by LSS. |
|
0855
|
Rig into hole with NGT-LSS-DITE(+TAP). |
|
1000
|
Log upward at 900 ft/hr from 593 mbsf to the end of pipe. |
|
1155
|
Tool back on rig floor. End of logging operations. Pull out of hole. |
Note: Drillers total depth = 2121 mbsf, water depth = 1427 mbrf, end of pipe = 101.7 mbsf. Tool acronyms are defined in "Downhole Measurements" in the "Explanatory Notes" chapter.