Step
|
Date (July 1999)
|
Time
|
Total time
|
Description
|
|
|
|
|
Install cable reel stands and rig sheaves in moonpool |
1 |
23 |
22:30 |
0
|
Move strainmeter/stinger assembly to rig floor |
2 |
24 |
00:05 |
1:35
|
Make up stinger to strainmeter, vertical on rig floor |
3 |
24 |
00:20 |
1:50
|
Make up lifting eyes and landing brackets to strainmeter |
4 |
24 |
00:55 |
2:25:00
|
Make up 4.5-in casing joint to seismometer, vertically on deck; install centralizers on casing |
5 |
24 |
01:20 |
2:50:00
|
Make up seismometer to strainmeter; pick up instrument package and remove strainmeter landing brackets |
6 |
24 |
01:25 |
2:55:00
|
Slowly lower to moonpool |
7 |
24 |
02:10 |
3:40:00
|
Make up instrument cable connections in moonpool |
8 |
24 |
03:20 |
4:50:00
|
Begin strapping and wrapping cables |
9 |
24 |
04:15 |
5:45:00
|
Run 93 joints (~1074 m) of 4.5-in casing |
10 |
24 |
16:45 |
18:15:00
|
RIH (33 m); move hanger/riser on to rig floor |
11 |
24 |
18:15 |
19:45:00
|
Assemble hanger/riser to 4.5-in casing |
12 |
24 |
18:30 |
20:00:00
|
Cut cables to length |
13 |
24 |
19:15 |
20:45:00
|
Raise hanger/riser feeding free end of cables into subsea shop |
14 |
24 |
19:45 |
21:15:00
|
Make up cable terminations |
15 |
25 |
10:30 |
36:00:00
|
Install the MEG |
16 |
25 |
13:45 |
39:15:00
|
Deploy VIT |
17 |
25 |
18:00 |
43:30:00
|
RIH/wash to 23 m from TD/POOH-contingency |
18 |
26 |
17:30 |
67:00:00
|
RIH/ream |
19 |
27 |
09:00 |
82:30:00
|
Pick up instrumentation string/test/RIH |
20 |
27 |
16:30 |
90:00:00
|
RIH/wash to TD |
20 |
27 |
21:30 |
95:00:00
|
Land hanger/riser in reentry cone |
21 |
27 |
22:00 |
95:30:00
|
Pump 68 bbl 16 lb/gal (~2000 kg/m3) cement slurry/drop dart |
22 |
28 |
01:00 |
98:30:00
|
Prep battery frame in moonpool |
23 |
28 |
05:45 |
103:15:00
|
Deploy battery frame |
24 |
28 |
08:30 |
106:00:00
|
Battery frame land in cone |
25 |
28 |
12:50 |
110:20:00
|
J-joint disconnected |
26 |
28 |
19:00 |
116:30:00
|
POOH |