Table T23. Instrument package deployment, Site 1150.

Step
Date
(July
1999)
Time
Total time
Description


Install cable reel stands and rig sheaves in moonpool
1 23 22:30 0
Move strainmeter/stinger assembly to rig floor
2 24 00:05 1:35
Make up stinger to strainmeter, vertical on rig floor
3 24 00:20 1:50
Make up lifting eyes and landing brackets to strainmeter
4 24 00:55 2:25:00
Make up 4.5-in casing joint to seismometer, vertically on deck; install centralizers on casing
5 24 01:20 2:50:00
Make up seismometer to strainmeter; pick up instrument package and remove strainmeter landing brackets
6 24 01:25 2:55:00
Slowly lower to moonpool
7 24 02:10 3:40:00
Make up instrument cable connections in moonpool
8 24 03:20 4:50:00
Begin strapping and wrapping cables
9 24 04:15 5:45:00
Run 93 joints (~1074 m) of 4.5-in casing
10 24 16:45 18:15:00
RIH (33 m); move hanger/riser on to rig floor
11 24 18:15 19:45:00
Assemble hanger/riser to 4.5-in casing
12 24 18:30 20:00:00
Cut cables to length
13 24 19:15 20:45:00
Raise hanger/riser feeding free end of cables into subsea shop
14 24 19:45 21:15:00
Make up cable terminations
15 25 10:30 36:00:00
Install the MEG
16 25 13:45 39:15:00
Deploy VIT
17 25 18:00 43:30:00
RIH/wash to 23 m from TD/POOH-contingency
18 26 17:30 67:00:00
RIH/ream
19 27 09:00 82:30:00
Pick up instrumentation string/test/RIH
20 27 16:30 90:00:00
RIH/wash to TD
20 27 21:30 95:00:00
Land hanger/riser in reentry cone
21 27 22:00 95:30:00
Pump 68 bbl 16 lb/gal (~2000 kg/m3) cement slurry/drop dart
22 28 01:00 98:30:00
Prep battery frame in moonpool
23 28 05:45 103:15:00
Deploy battery frame
24 28 08:30 106:00:00
Battery frame land in cone
25 28 12:50 110:20:00
J-joint disconnected
26 28 19:00 116:30:00
POOH

Notes: Extra time due to contingency on 25 July 1999, 18:00 hr, through 27 July 1999, 16:30 hr = 46.5 hr. RIH = run in hole, VIT = vibration isolated television, TD = total depth, POOH = pull out of hole.