Table T19. Instrument package deployment, Site 1151.

Step Date
(Aug 1999)
Time (local) Total Time Description



  Install cable reel stands and rig sheaves in moonpool; make up stinger to strainmeter; make up lifting eyes and landing brackets to strainmeter
1
7
11:30 0 Move strainmeter/stinger assembly to rig floor
2
7
11:45 0:15:00 Make up 4.5-in casing joint to seismometer, horizontal on deck
3
7
12:15 0:45:00 Make up seismometer to strainmeter; pick up instrument package and remove strainmeter landing brackets
4
7
12:45 1:15:00 Slowly lower to moonpool; make up instrument cable connections in moonpool
5
7
13:00 1:30:00 Begin strapping and wrapping cables
6
7
13:15 1:45:00 Run 39 joints (~454 m) of 4.5-in casing, install circulating sub, 51 joints (594 m) of 4.5-in casing
7
7
22:00 10:30:00 Run in hole with two more joints of 4.5-in casing
8
7
22:30 11:00:00 Move hanger/riser onto rig floor
9
7
23:30 12:00:00 Make up hanger/riser to 4.5-in casing
10
7
23:45 12:15:00 Cut cables to length
11
8
0:15 12:30:00 Raise hanger/riser feeding free end of cables into subsea shop
12
8
0:30 13:00:00 Make up cable terminations
13
8
12:30 25:00:00 Install G-Box
14
8
14:45 27:15:00 Remove, troubleshoot, and reinstall MEG
15
8
18:45 31:15:00 Test VIT over riser/hanger
16
8
19:15 31:45:00 Run in hole/deploy VIT
17
8
21:45 34:15:00 Wash to total depth/land hanger/riser in reentry cone
18
9
0:45 37:15:00 Lower VIT/check installation
19
9
1:00 37:30:00 Pump 80 bbl 16 lb/gal (~1900 kg/m3) cement slurry/drop dart
20
9
3:30 40:00:00 Prepare battery frame in moonpool
21
9
6:15 42:45:00 Deploy battery frame
22
9
9:00 45:30:00 Battery frame land in cone
23
9
9:00 45:30:00 Release/recover log line/pull out of hole/VIT
24
9
12:15 48:45:00 J-joint disconnected
25
9
17:15 53:45:00 Pull out of hole

Notes: Extra time due to contingency 8 Aug 14:45-18:45 (4 hr). MEG = multiple-access expandable gateway, VIT = vibration isolated television.