Table T19. Instrument package deployment, Site 1151.
Step | Date (Aug 1999) |
Time (local) | Total Time | Description |
---|---|---|---|---|
Install cable reel stands and rig sheaves in moonpool; make up stinger to strainmeter; make up lifting eyes and landing brackets to strainmeter | ||||
1 |
7
|
11:30 | 0 | Move strainmeter/stinger assembly to rig floor |
2 |
7
|
11:45 | 0:15:00 | Make up 4.5-in casing joint to seismometer, horizontal on deck |
3 |
7
|
12:15 | 0:45:00 | Make up seismometer to strainmeter; pick up instrument package and remove strainmeter landing brackets |
4 |
7
|
12:45 | 1:15:00 | Slowly lower to moonpool; make up instrument cable connections in moonpool |
5 |
7
|
13:00 | 1:30:00 | Begin strapping and wrapping cables |
6 |
7
|
13:15 | 1:45:00 | Run 39 joints (~454 m) of 4.5-in casing, install circulating sub, 51 joints (594 m) of 4.5-in casing |
7 |
7
|
22:00 | 10:30:00 | Run in hole with two more joints of 4.5-in casing |
8 |
7
|
22:30 | 11:00:00 | Move hanger/riser onto rig floor |
9 |
7
|
23:30 | 12:00:00 | Make up hanger/riser to 4.5-in casing |
10 |
7
|
23:45 | 12:15:00 | Cut cables to length |
11 |
8
|
0:15 | 12:30:00 | Raise hanger/riser feeding free end of cables into subsea shop |
12 |
8
|
0:30 | 13:00:00 | Make up cable terminations |
13 |
8
|
12:30 | 25:00:00 | Install G-Box |
14 |
8
|
14:45 | 27:15:00 | Remove, troubleshoot, and reinstall MEG |
15 |
8
|
18:45 | 31:15:00 | Test VIT over riser/hanger |
16 |
8
|
19:15 | 31:45:00 | Run in hole/deploy VIT |
17 |
8
|
21:45 | 34:15:00 | Wash to total depth/land hanger/riser in reentry cone |
18 |
9
|
0:45 | 37:15:00 | Lower VIT/check installation |
19 |
9
|
1:00 | 37:30:00 | Pump 80 bbl 16 lb/gal (~1900 kg/m3) cement slurry/drop dart |
20 |
9
|
3:30 | 40:00:00 | Prepare battery frame in moonpool |
21 |
9
|
6:15 | 42:45:00 | Deploy battery frame |
22 |
9
|
9:00 | 45:30:00 | Battery frame land in cone |
23 |
9
|
9:00 | 45:30:00 | Release/recover log line/pull out of hole/VIT |
24 |
9
|
12:15 | 48:45:00 | J-joint disconnected |
25 |
9
|
17:15 | 53:45:00 | Pull out of hole |
Notes: Extra time due to contingency 8 Aug 14:45-18:45 (4 hr). MEG = multiple-access expandable gateway, VIT = vibration isolated television.