Table T20. Instrument package deployment, Site 1179.

Step
Start
time/date
Cumulative time
(hh:mm:ss)
Description
0 1445 21 Aug
Make up seismometer string; weld lifting eyes to battery frame; move battery frame to moonpool; install cable reel stands and rig sheaves in moonpool
1 1557 21 Aug 0 Move seismometer string to rig floor
2 1608 21 Aug 0:11:00 Make up 4.5-in casing joint to seismometer, horizontal on deck
3 1627 21 Aug 0:30:00 Pick up seismometer and make up seismometer to stinger
4 1635 21 Aug 0:38:00 Slowly lower stinger/seismometer into moonpool
5 1643 21 Aug 0:46:00 Make up instrument cable connections in moonpool
6 1757 21 Aug 2:00:00 Test seismometer through instrument cable
7 1813 21 Aug 2:16:00 Begin strapping and wrapping two cables as instrument package is lowered; install centralizers
8 1830 21 Aug 2:33:00 Run 39 joints (~454 m) of 4.5-in casing
9 0215 22 Aug 10:18:00 Move hanger/riser on rig floor
10 0302 22 Aug 11:05:00 Make up hanger/riser to 4.5-in casing
11 0330 22 Aug 11:33:00 Pick up hanger/riser and lower to moonpool level
12 0435 22 Aug 12:38:00 Cut two cables to length
13 0444 22 Aug 12:47:00 Raise hanger/riser, feeding free end of cables into subsea shop
14 0500 22 Aug 13:03:00 Make up cable terminations
15 2210 22 Aug 30:13:00 Make up cables to the multiple-access expandable gateway
16 0016 23 Aug 32:19:00 Test seismometer/multiple-access expandable gateway
17 0102 23 Aug 33:05:00 Test vibration-isolated television over riser/hanger
18 0130 23 Aug 33:33:00 Lower landing assembly of seismometer
19 0945 23 Aug 41:48:00 Reenter (~11 hr, 15 min); lower vibration-isolated television and inspect installation
20 1500 23 Aug 47:03:00 Land hanger/riser in reentry cone



Maintain compression on hanger/riser to prevent it from lifting off the landing seat
21 1515 23 Aug 47:18:00 Pump 50 bbl of 15.8 lb/gal (~1900 kg/m3) cement slurry/drop dart; recover vibration-isolated television
22 2000 23 Aug 52:03:00 Prepare battery frame in moonpool; test power control system/storage acquisition module (~0130 hr)
23 0023 24 Aug 56:26:00 Attach bridle assembly to battery frame; wait on daylight
24 0415 24 Aug 60:18:00 Slowly lower battery frame on logging line to reentry cone
25 0905 24 Aug 65:08:00 Land battery frame in cone; activate acoustic release; recover logging line/bridal assembly/acoustic releaser
26 1229 24 Aug 68:32:00 Lower vibration-isolated television to inspect
27 1445 24 Aug 70:48:00 Release running tool

Note: This table is also available in ASCII format.