Table T1. Chronologic operations summary.
 
Date (2000) LocationTask
Start Finish
7 Nov 14 Nov Port call
14 Nov 18 Nov Transit
18 Nov 22 Nov Hole 1188A RCB coring
22 Nov 23 Nov Hole 1189A RCB coring
23 Nov 25 Nov Holes 1190A, 1190B, 1190C RCB coring
25 Nov 27 Nov Hole 1188B RAB/LWD/ADCB
27 Nov 28 Nov Site 1191 RCB coring
28 Nov 1 Dec Holes 1188C, 1188D, 1188E No coring
1 Dec 12 Dec Hole 1188F Casing
12 Dec 21 Dec Hole 1188F ADCB coring/logging
21 Dec 22 Dec Hole 1188F Water sampling/temperature measurements
22 Dec 26 Dec Hole 1189B HRRS casing/RCB coring/logging
27 Dec 29 Dec Holes 1189C, 1188F RAB/LWD/logging, temperature measurements/water sampling

Notes: RCB = rotary core barrel, RAB = resistivity at bit, LWD = logging while drilling, ADCB = advanced diamond core barrel, HRRS = hard-rock reentry system.