25 | 0530 | Hole preparation complete. Rig up wireline. |
0715 | RIH with MGT-HNGS-APS-HLDS-DITE (+TAP). | |
0755 | Uplog with triple combo at 900 ft/hr from 425 mbsf to seafloor. Rig into hole to TD. | |
0950 | Uplog with MGT at 700 ft/hr from 425 to 75 mbsf. Rig into hole for short repeat. | |
1135 | Uplog with MGT at 700 ft/hr from 134.5 to 65 mbsf. Pull out of hole. | |
1345 | Rig up NGT-DSI-FMS. | |
1425 | RIH with NGT-DSI-FMS. | |
1515 | Uplog at 900 ft/hr from 425 mbsf to pipe. Pull out of hole. | |
1630 | Rig up NGT-LSS-FMS. | |
1810 | Uplog at 900 ft/hr from 425 to pipe. Pull out of hole. | |
2130 | Rig up WST. | |
1045 | Tight spot prevents the tool from going deeper than 157 mbsf. Start check shots. | |
1150 | Pull out of hole and rig down. | |
26 | 0030 | End of logging operations. |
Notes: RIH = run in hole, MGT = Lamont multisensor gamma ray tool, HNGS = hostile-environment natural gamma ray sonde, APS = accelerator porosity sonde, HLDS = high-temperature lithodensity sonde, DITE = dual induction tool, TAP = high-temperature/acceleration/pressure tool. TD = total depth. NGT = natural gamma ray tool, DSI = dipole shear sonic imager, FMS = Formation MicroScanner, LSS = long-spaced sonic tool, WST = well seismic tool. Drillers total depth = 427.1 mbsf, water depth = 384.8 mbrf, end of pipe = 78.93 mbsf.