Date
(Jan. 2001) |
Time
(local) |
Comments
|
|---|---|---|
| 29 | 0305 | Hole preparation complete; rig up wireline. |
| 0450 | RIH with MGT-HNGS-APS-HLDS-DITE (+TAP). | |
| 0525 | Tools cannot pass bottom of pipe. Pull tools back in pipe; start pumping water through pipe. | |
| 0625 | Tools reach bottom of hole. | |
| 0630 | Uplog with triple combo at 900 ft/hr from 518.5 mbsf to seafloor. | |
| 1030 | Rig up WST. | |
| 1130 | Tool cannot pass bottom of pipe. Tool pulled back on deck; start wiper trip. | |
| 1600 | RIH with WST. | |
| 1640 | Tight spot prevents the tool from going deeper than 121 mbsf. Start check shots. | |
| 1735 | Pull out of hole and rig down. | |
| 1740 | End of logging operations. |
Notes: RIH = run in hole, MGT = multisensor gamma ray tool, HNGS = hostile environment natural gamma ray sonde, APS = accelerator porosity sonde, HLDS = high-temperature lithodensity sonde, DITE = dual induction tool, TAP = high-temperature/acceleration/pressure tool, WST = well seismic tool. Drillers total depth = 520.44 mbsf, water depth = 430.8 mbrf, end of pipe = 98.7 mbsf.
![]()