Table T4. Operation synopsis, Leg 200.
Site/Hole
Activity
Local time
(hr)
Date
Time
on hole
(hr)
Time
on site
(hr)
Comments
Port call Honolulu First line ashore 0752 16 Dec 2001



Leg 200 Last line aboard 1404 20 Dec 2001 102.20
102.20





Total: 102.20
Honolulu Depart 1404 20 Dec 2001




End of sea voyage Nuuanu 0730 21 Dec 2001 17.43
17.43 Traveled 175 nmi at 10.0 kt





Total: 17.43








1223A Position on GPS 0730 21 Dec 2001


Spud at 2030 hr

Spud Hole 1223A 2030 21 Dec 2001 13.00
13.00 Run in hole

Clear seafloor Hole 1223A 1725 22 Dec 2001 20.92
20.92 Science objective obtained

Clear rotary 0130 23 Dec 2001 8.08
8.08 Pull out of hole

Depart site 0130 23 Dec 2001 0.00
0.00





Total: 42.00
Nuuanu Depart site 0130 23 Dec 2001




Arrive at H2O 0000 26 Dec 2001 70.50
70.50 Traveled 766 nmi at 10.9 kt

Seismic survey 0745 26 Dec 2001 7.75
7.75 Mechanical breakdown 43 nmi at 5.5 kt





Total: 78.25

ODP mechanical downtime



7.75








1224A Arrive on location 0745 26 Dec 2001




Position on GPS 0845 26 Dec 2001 1.00
1.00 On location in DP mode

Waiting on weather 2200 26 Dec 2001 13.25
13.25

Run in hole 1230 27 Dec 2001 14.50
14.50

Box survey 1430 27 Dec 2001 2.00
2.00 Tag seafloor for jet-in 1525 hr

Jet-in test 1715 27 Dec 2001 2.75
2.75 Finish jet-in 1715 hr

Pull out of hole 1745 27 Dec 2001 0.50
0.50 Clear seafloor at 1740 hr

Retrieve VIT 0000 28 Dec 2001 6.25
6.25

Hang off drill string 0030 28 Dec 2001 0.50
0.50

Waiting on weather 1345 28 Dec 2001 13.25
13.25

Drop core barrel 1455 28 Dec 2001 1.17
1.17

Spud Hole 1224A 1455 28 Dec 2001

0.00

Clear seafloor 0530 29 Dec 2001 14.58
14.58





Total: 69.75

Hole 1224A waiting on weather



33.25








1224B Offset 0530 29 Dec 2001




Spud Hole 1224B 0650 29 Dec 2001 1.33
1.33 APC for mudline

Clear seafloor 0745 29 Dec 2001 0.92
0.92 Mechanical shear





Total: 2.25








1224C Run in hole with core barrel 0745 29 Dec 2001

0.00 APC for mudline

Spud Hole 1224C 0820 29 Dec 2001 0.58
0.58

Clear seafloor 0915 29 Dec 2001 0.92
0.92

Hang off drill string 1000 29 Dec 2001 0.75
0.75

Waiting on weather 0115 30 Dec 2001 15.25
15.25

Jet-in test spud 0118 hr 0230 30 Dec 2001 1.25
1.25 Cleared seafloor at 0230 hr

Cleared rotary 1430 30 Dec 2001 12.00
12.00 Pull out of hole





Total: 30.75

Hole 1224C waiting on weather



16.00








1224D Pick up casing tools and






position reentry cone 1830 30 Dec 2001 4.00
4.00 Arrive hole

Waiting on weather 1715 1 Jan 2002 46.75
46.75

Launch reentry assembly 2335 1 Jan 2002 6.33
6.33 Make up casing and BHA

Spud Hole 1224D 1220 2 Jan 2002 12.75
12.75 Run in hole and space out to jet-in

Release running tool 1300 2 Jan 2002 0.67
0.67 Jet-in 20-in casing







20-in casing at 25.47 mbsf

Cleared seafloor 1315 2 Jan 2002




Cleared rotary 0200 3 Jan 2002 13.00
13.00 Pull out of hole for RCB BHA

Install upper guide horn 0300 3 Jan 2002 1.00
1.00

Detorque CHRT 0315 3 Jan 2002 0.25
0.25

Slip and cut drilling line 0445 3 Jan 2002 1.50
1.50





Total: 86.25









Make up RCB BHA and run in hole 1800 3 Jan 2002 13.25
13.25

Search and reenter 1845 3 Jan 2002 0.75
0.75 Reenter Hole 1224D 1837 hr

Run in hole to 20-in shoe 25.5 m 1915 3 Jan 2002 0.50
0.50

Recover VIT 2130 3 Jan 2002 2.25
2.25

RCB 25.5-51.3 m 0430 5 Jan 2002 31.00
31.00 Tag hard at 29.5 m (0.8 m/hr)

Pull out of hole into casing 0500 5 Jan 2002 0.50
0.50 Increasing heave and roll

Retrieve Core 4R 0600 5 Jan 2002 1.00
1.00

Waiting on weather 0945 5 Jan 2002 3.75
3.75

Run in hole 1015 5 Jan 2002 0.50
0.50

RCB 51.3-59.0 mbsf 2245 5 Jan 2002 12.50
12.50 Cored Hole 1224D TD

Pull out of hole into casing 2345 5 Jan 2002 1.00
1.00

Retrieve Core 5R 0100 6 Jan 2002 1.25
1.25

Waiting on weather 0045 7 Jan 2002 23.75
23.75 Pull out of hole into casing and pull out of hole to 4907 mbrf

Clear seafloor 1000 6 Jan 2002


Reentry required to core ahead


0045 7 Jan 2002


Pull out of hole preparation good weather

Pull out of hole for 143/4-in bit 1100 7 Jan 2002 10.25
10.25 Clear rotary at 1100 hr

Prepare cement manifold 1200 7 Jan 2002 1.00
1.00

Make up running tool 1400 7 Jan 2002 2.00
2.00

Make up 143/4 BHA 1715 7 Jan 2002 3.25
3.25 Strip upper guide horn

Run in hole to 4790 m 2345 7 Jan 2002 6.50
6.50

Hang off DP on rotary 0000 8 Jan 2002 0.25
0.25

Waiting on weather 1200 8 Jan 2002 12.00
12.00

Launch VIT 1330 8 Jan 2002 1.50
1.50

Run in hole, space out for reentry 1500 8 Jan 2002 1.50
1.50

Reentry Hole 1224D 1515 8 Jan 2002 0.25
0.25 Reenter Hole 1224D at 1515 hr

Run in hole to 23.84 mbsf 1530 8 Jan 2002 0.25
0.25

Pull out of hole with VIT 1845 8 Jan 2002 3.25
3.25

Open hole to 143/4 in 1515 9 Jan 2002 20.50
20.50 AHC shut down at 1515 hr

Open hole to 143/4 in 1500 10 Jan 2002 23.75
23.75 To RCB TD of 59 mbsf

Drill hole for 143/4 in 0730 11 Jan 2002 16.50
16.50 Excess torque from 62.7 mbsf







TD Hole 1224D at 64.7 mbsf

Short trip to casing shoe 0830 11 Jan 2002 1.00
1.00 Condition hole

Run in hole and tag bottom 0915 11 Jan 2002 0.75
0.75 Tag 64.7 with 0.5 m soft fill

Displace hole to mud 1000 11 Jan 2002 0.75
0.75 Circulate hole for casing

Pull out of hole 2030 11 Jan 2002 10.50
10.50 Clear seafloor at 1100 hr







Clear rotary at 2025 hr

Rig up to run 103/4 -in casing 0000 12 Jan 2002 3.50
3.50 Deploy casing at 2355 hr

Run in hole with casing 1300 12 Jan 2002 13.00
13.00 TD 10 -in casing at 58.47 mbsf

Reentry Hole 1224D 1330 12 Jan 2002 0.50
0.50 Reenter Hole 1224D at 1336 hr

Run in hole, space out to land casing 1515 12 Jan 2002 1.75
1.75 Land 10 casing at 1515 hr

Cement with 18.8 bbl of 15.5 ppg 1645 12 Jan 2002 1.50
1.50 Release dart at 1635 hr







Bump plug with 900 psi; no flowback

Release running tool from casing 1715 12 Jan 2002 0.50
0.50 Release on second attempt at 1715 hr

Recover VIT 2000 12 Jan 2002 2.75
2.75

Slip and cut drill line 2115 12 Jan 2002 1.25
1.25 Clear seafloor at 1715 hr

Pull out of hole 0600 13 Jan 2002 8.75
8.75 Clear rotary at 0530 hr

Make up BHA and run in hole 1600 13 Jan 2002 10.00
10.00 Clean out Hole 1224D inside casing

Reenter Hole 1224D 1630 13 Jan 2002 0.50
0.50 Reenter Hole 1224D at 1630 hr







Reentry cone sank 1.75 m

Wash out soft cement 1715 13 Jan 2002 0.75
0.75 54.6-58.1 mbsf

Circulate casing clean 1745 13 Jan 2002 0.50
0.50 Science objective obtained

Pull out of hole 1815 13 Jan 2002 0.50
0.50 Clear seafloor at 1817 hr





Total: 253.50

Hole 1224D waiting on weather



97.50








1224E Offset 15 m southwest 1845 13 Jan 2002 0.50
0.50

Tag seafloor at 4978 mbrf 1900 13 Jan 2002 0.25
0.25 Tag seafloor at 1840 hr

Wash, punch Cores 1R and 2R 2215 13 Jan 2002 3.25
3.25 0-8 mbsf; 8-27.1 mbsf

3R, 27.1-36.7 mbsf 1500 14 Jan 2002 16.75
16.75 Tag hard at 27.7 mbsf

Cleared seafloor 1500 14 Jan 2002 0.00
0.00 Pulled out of basement





Total: 20.75
1224F Looking for Hole 1224E 1630 14 Jan 2002 1.50
1.50 Pulled out of basement as pulled out of hole

Spud hole 1630 14 Jan 2002




Core 1R, 27.7-39.70 mbsf 0455 15 Jan 2002 12.42
12.42 New hole with bare rock spud

Cores 2R-4R, 39.70-65.90 mbsf 0650 16 Jan 2002 25.92
25.92 Flow basalt and high recovery







Drilling break 62.7 mbsf, Hole 1224D

Cores 5R-11R, 65.9-128.50 mbsf 2315 17 Jan 2002 40.42
40.42 Altered basalt poor recovery

Short trip for knobbies 0115 18 Jan 2002 2.00
2.00 Pull out of hole above basement contact

Search for and reenter Hole F 0200 18 Jan 2002 0.75
0.75

Run in hole from 25.69-93.16 mbsf 0330 18 Jan 2002 1.50
1.50

TSF mechanical breakdown 0700 18 Jan 2002 3.50
3.50 Repack swivel on top drive

Run in hole from 93.16-128.5 mbsf 0830 18 Jan 2002 1.50
1.50 12-m soft fill circulated out

Cores 12R-14R, 128.5-143 mbsf 1700 18 Jan 2002 8.50
8.50 3-m fill on Core 14R

Work pipe to clean hole 1745 18 Jan 2002 0.75
0.75 400 amp and 4-m fill

Cores 14R-16R, 143-171 mbsf 1700 19 Jan 2002 23.25
23.25 Zero recovery Core 16R

Run bit deplugger 2015 19 Jan 2002 3.25
3.25 Did not appear to seat in bit

Core 17R, 171-174.5 mbsf 2245 19 Jan 2002 2.50
2.50 Zero recovery Core 17R

Run in hole with rotary shifter tool 0000 20 Jan 2002 1.25
1.25 Drop bit at 2320 hr

Displace hole for logging 0045 20 Jan 2002 0.75
0.75

Pull out of hole for logging 0230 20 Jan 2002 1.75
1.75 EOP 49.94 mbsf

Drop FFF 0515 20 Jan 2002 2.75
2.75

Rig up and run log 1 1615 20 Jan 2002 11.00
11.00 DITE/HLDT/APS/HNGS







In at 0745 hr, depth 5152 m; out at 1520 hr

Rig up and run log 2 1945 20 Jan 2002 3.50
3.50 FMS/NGT/DSI







Misrun replace telemetry tool

Log 2 in 1945 20 Jan 2002 0.00
0.00 Depth 5152 m (174 mbsf)

Log 2 out 0530 21 Jan 2002 9.75
9.75 Out at 0525 hr

Rig up and run log 3 0945 21 Jan 2002 4.25
4.25 WST in; 0745 hr misrun







Depth 1057 m, out at 0945 hr

Rig down logging 1030 21 Jan 2002 0.75
0.75

Pull upper guide horn and launch VIT 1100 21 Jan 2002 0.50
0.50

Run in hole with VIT to observe FFF 1230 21 Jan 2002 1.50
1.50 Observe FFF at 1225 hr

Clear seafloor 1238 21 Jan 2002 0.13
0.13

Pull out of hole with DP and VIT 1415 21 Jan 2002 1.62
1.62

Recover VIT 1500 21 Jan 2002 0.75
0.75

1st beacon on deck 1612 21 Jan 2002




2nd beacon on deck 1800 21 Jan 2002




Pull out of hole with DP to 112.92 mbrf 2115 21 Jan 2002 6.25
6.25

MBR clear rotary 2355 21 Jan 2002




Lay out DC to catwalk 0000 22 Jan 2002 2.75
2.75

Secure ship for sea voyage 0030 22 Jan 2002 0.50
0.50 Depart site at 0030 hr

Seismic survey over H2O-5 (Site 1224) 0145 22 Jan 2002 1.25
1.25 Functional test





Total: 178.75









Hole 1224F






TSF mechanical downtime



3.50

LDEO logging downtime



7.75

ODP mechanical downtime



0.00
H2O-5 (Site 1224) Depart site 0145 22 Jan 2002



San Diego End of sea voyage (pilot aboard) 0700 27 Jan 2002 125.25
125.25 Traveled 1320 nmi at 10.49 kt

First line ashore 0820 27 Jan 2002

1.33





Total: 126.58


Total hours:

779.68


Total days:

32.49

Note: GPS = global positioning system, DP = drill pipe, VIT = vibration isolated television, APC = advanced piston corer, BHA = bottom-hole assembly, CHRT = casing hanger running tool, RCB = rotary core barrel, TD = total depth, AHC = active heave compensator, EOP = end of pipe, FFF = free-fall funnel, DITE = Digital Dual Induction Tool model E, HLDT = Hostile Environment Litho-Density Tool, APS = accelerator porosity sonde, HNGS = Hostile Environment Natural Gamma Ray Sonde, FMS = Formation MicroScanner, NGT = Natural Gamma Spectrometry Tool, DSI = Dipole Sonic Imager, WST = Well Seismic Tool, DC = drill collar, MBR = mechanical bit release, TSF = Transocean Sedco Forex.