Site/Hole
|
Activity
|
Local time
(hr)
|
Date
|
Time
on hole
(hr)
|
|
Time
on site
(hr)
|
Comments
|
---|---|---|---|---|---|---|---|
Port call Honolulu | First line ashore | 0752 | 16 Dec 2001 |
|
|
|
|
Leg 200 | Last line aboard | 1404 | 20 Dec 2001 | 102.20 |
|
102.20 |
|
|
|
|
|
|
Total: | 102.20 |
|
Honolulu | Depart | 1404 | 20 Dec 2001 |
|
|
|
|
|
End of sea voyage Nuuanu | 0730 | 21 Dec 2001 | 17.43 |
|
17.43 | Traveled 175 nmi at 10.0 kt |
|
|
|
|
|
Total: | 17.43 |
|
|
|
|
|
|
|
|
|
1223A | Position on GPS | 0730 | 21 Dec 2001 |
|
|
|
Spud at 2030 hr |
|
Spud Hole 1223A | 2030 | 21 Dec 2001 | 13.00 |
|
13.00 | Run in hole |
|
Clear seafloor Hole 1223A | 1725 | 22 Dec 2001 | 20.92 |
|
20.92 | Science objective obtained |
|
Clear rotary | 0130 | 23 Dec 2001 | 8.08 |
|
8.08 | Pull out of hole |
|
Depart site | 0130 | 23 Dec 2001 | 0.00 |
|
0.00 |
|
|
|
|
|
|
Total: | 42.00 |
|
Nuuanu | Depart site | 0130 | 23 Dec 2001 |
|
|
|
|
|
Arrive at H2O | 0000 | 26 Dec 2001 | 70.50 |
|
70.50 | Traveled 766 nmi at 10.9 kt |
|
Seismic survey | 0745 | 26 Dec 2001 | 7.75 |
|
7.75 | Mechanical breakdown 43 nmi at 5.5 kt |
|
|
|
|
|
Total: | 78.25 |
|
|
ODP mechanical downtime |
|
|
|
|
7.75 |
|
|
|
|
|
|
|
|
|
1224A | Arrive on location | 0745 | 26 Dec 2001 |
|
|
|
|
|
Position on GPS | 0845 | 26 Dec 2001 | 1.00 |
|
1.00 | On location in DP mode |
|
Waiting on weather | 2200 | 26 Dec 2001 | 13.25 |
|
13.25 |
|
|
Run in hole | 1230 | 27 Dec 2001 | 14.50 |
|
14.50 |
|
|
Box survey | 1430 | 27 Dec 2001 | 2.00 |
|
2.00 | Tag seafloor for jet-in 1525 hr |
|
Jet-in test | 1715 | 27 Dec 2001 | 2.75 |
|
2.75 | Finish jet-in 1715 hr |
|
Pull out of hole | 1745 | 27 Dec 2001 | 0.50 |
|
0.50 | Clear seafloor at 1740 hr |
|
Retrieve VIT | 0000 | 28 Dec 2001 | 6.25 |
|
6.25 |
|
|
Hang off drill string | 0030 | 28 Dec 2001 | 0.50 |
|
0.50 |
|
|
Waiting on weather | 1345 | 28 Dec 2001 | 13.25 |
|
13.25 |
|
|
Drop core barrel | 1455 | 28 Dec 2001 | 1.17 |
|
1.17 |
|
|
Spud Hole 1224A | 1455 | 28 Dec 2001 |
|
|
0.00 |
|
|
Clear seafloor | 0530 | 29 Dec 2001 | 14.58 |
|
14.58 |
|
|
|
|
|
|
Total: | 69.75 |
|
|
Hole 1224A waiting on weather |
|
|
|
|
33.25 |
|
|
|
|
|
|
|
|
|
1224B | Offset | 0530 | 29 Dec 2001 |
|
|
|
|
|
Spud Hole 1224B | 0650 | 29 Dec 2001 | 1.33 |
|
1.33 | APC for mudline |
|
Clear seafloor | 0745 | 29 Dec 2001 | 0.92 |
|
0.92 | Mechanical shear |
|
|
|
|
|
Total: | 2.25 |
|
|
|
|
|
|
|
|
|
1224C | Run in hole with core barrel | 0745 | 29 Dec 2001 |
|
|
0.00 | APC for mudline |
|
Spud Hole 1224C | 0820 | 29 Dec 2001 | 0.58 |
|
0.58 |
|
|
Clear seafloor | 0915 | 29 Dec 2001 | 0.92 |
|
0.92 |
|
|
Hang off drill string | 1000 | 29 Dec 2001 | 0.75 |
|
0.75 |
|
|
Waiting on weather | 0115 | 30 Dec 2001 | 15.25 |
|
15.25 |
|
|
Jet-in test spud 0118 hr | 0230 | 30 Dec 2001 | 1.25 |
|
1.25 | Cleared seafloor at 0230 hr |
|
Cleared rotary | 1430 | 30 Dec 2001 | 12.00 |
|
12.00 | Pull out of hole |
|
|
|
|
|
Total: | 30.75 |
|
|
Hole 1224C waiting on weather |
|
|
|
|
16.00 |
|
|
|
|
|
|
|
|
|
1224D | Pick up casing tools and |
|
|
|
|
|
|
|
position reentry cone | 1830 | 30 Dec 2001 | 4.00 |
|
4.00 | Arrive hole |
|
Waiting on weather | 1715 | 1 Jan 2002 | 46.75 |
|
46.75 |
|
|
Launch reentry assembly | 2335 | 1 Jan 2002 | 6.33 |
|
6.33 | Make up casing and BHA |
|
Spud Hole 1224D | 1220 | 2 Jan 2002 | 12.75 |
|
12.75 | Run in hole and space out to jet-in |
|
Release running tool | 1300 | 2 Jan 2002 | 0.67 |
|
0.67 | Jet-in 20-in casing |
|
|
|
|
|
|
|
20-in casing at 25.47 mbsf |
|
Cleared seafloor | 1315 | 2 Jan 2002 |
|
|
|
|
|
Cleared rotary | 0200 | 3 Jan 2002 | 13.00 |
|
13.00 | Pull out of hole for RCB BHA |
|
Install upper guide horn | 0300 | 3 Jan 2002 | 1.00 |
|
1.00 |
|
|
Detorque CHRT | 0315 | 3 Jan 2002 | 0.25 |
|
0.25 |
|
|
Slip and cut drilling line | 0445 | 3 Jan 2002 | 1.50 |
|
1.50 |
|
|
|
|
|
|
Total: | 86.25 |
|
|
|
|
|
|
|
|
|
|
Make up RCB BHA and run in hole | 1800 | 3 Jan 2002 | 13.25 |
|
13.25 |
|
|
Search and reenter | 1845 | 3 Jan 2002 | 0.75 |
|
0.75 | Reenter Hole 1224D 1837 hr |
|
Run in hole to 20-in shoe 25.5 m | 1915 | 3 Jan 2002 | 0.50 |
|
0.50 |
|
|
Recover VIT | 2130 | 3 Jan 2002 | 2.25 |
|
2.25 |
|
|
RCB 25.5-51.3 m | 0430 | 5 Jan 2002 | 31.00 |
|
31.00 | Tag hard at 29.5 m (0.8 m/hr) |
|
Pull out of hole into casing | 0500 | 5 Jan 2002 | 0.50 |
|
0.50 | Increasing heave and roll |
|
Retrieve Core 4R | 0600 | 5 Jan 2002 | 1.00 |
|
1.00 |
|
|
Waiting on weather | 0945 | 5 Jan 2002 | 3.75 |
|
3.75 |
|
|
Run in hole | 1015 | 5 Jan 2002 | 0.50 |
|
0.50 |
|
|
RCB 51.3-59.0 mbsf | 2245 | 5 Jan 2002 | 12.50 |
|
12.50 | Cored Hole 1224D TD |
|
Pull out of hole into casing | 2345 | 5 Jan 2002 | 1.00 |
|
1.00 |
|
|
Retrieve Core 5R | 0100 | 6 Jan 2002 | 1.25 |
|
1.25 |
|
|
Waiting on weather | 0045 | 7 Jan 2002 | 23.75 |
|
23.75 | Pull out of hole into casing and pull out of hole to 4907 mbrf |
|
Clear seafloor | 1000 | 6 Jan 2002 |
|
|
|
Reentry required to core ahead |
|
|
0045 | 7 Jan 2002 |
|
|
|
Pull out of hole preparation good weather |
|
Pull out of hole for 143/4-in bit | 1100 | 7 Jan 2002 | 10.25 |
|
10.25 | Clear rotary at 1100 hr |
|
Prepare cement manifold | 1200 | 7 Jan 2002 | 1.00 |
|
1.00 |
|
|
Make up running tool | 1400 | 7 Jan 2002 | 2.00 |
|
2.00 |
|
|
Make up 143/4 BHA | 1715 | 7 Jan 2002 | 3.25 |
|
3.25 | Strip upper guide horn |
|
Run in hole to 4790 m | 2345 | 7 Jan 2002 | 6.50 |
|
6.50 |
|
|
Hang off DP on rotary | 0000 | 8 Jan 2002 | 0.25 |
|
0.25 |
|
|
Waiting on weather | 1200 | 8 Jan 2002 | 12.00 |
|
12.00 |
|
|
Launch VIT | 1330 | 8 Jan 2002 | 1.50 |
|
1.50 |
|
|
Run in hole, space out for reentry | 1500 | 8 Jan 2002 | 1.50 |
|
1.50 |
|
|
Reentry Hole 1224D | 1515 | 8 Jan 2002 | 0.25 |
|
0.25 | Reenter Hole 1224D at 1515 hr |
|
Run in hole to 23.84 mbsf | 1530 | 8 Jan 2002 | 0.25 |
|
0.25 |
|
|
Pull out of hole with VIT | 1845 | 8 Jan 2002 | 3.25 |
|
3.25 |
|
|
Open hole to 143/4 in | 1515 | 9 Jan 2002 | 20.50 |
|
20.50 | AHC shut down at 1515 hr |
|
Open hole to 143/4 in | 1500 | 10 Jan 2002 | 23.75 |
|
23.75 | To RCB TD of 59 mbsf |
|
Drill hole for 143/4 in | 0730 | 11 Jan 2002 | 16.50 |
|
16.50 | Excess torque from 62.7 mbsf |
|
|
|
|
|
|
|
TD Hole 1224D at 64.7 mbsf |
|
Short trip to casing shoe | 0830 | 11 Jan 2002 | 1.00 |
|
1.00 | Condition hole |
|
Run in hole and tag bottom | 0915 | 11 Jan 2002 | 0.75 |
|
0.75 | Tag 64.7 with 0.5 m soft fill |
|
Displace hole to mud | 1000 | 11 Jan 2002 | 0.75 |
|
0.75 | Circulate hole for casing |
|
Pull out of hole | 2030 | 11 Jan 2002 | 10.50 |
|
10.50 | Clear seafloor at 1100 hr |
|
|
|
|
|
|
|
Clear rotary at 2025 hr |
|
Rig up to run 103/4 -in casing | 0000 | 12 Jan 2002 | 3.50 |
|
3.50 | Deploy casing at 2355 hr |
|
Run in hole with casing | 1300 | 12 Jan 2002 | 13.00 |
|
13.00 |
TD 10![]() |
|
Reentry Hole 1224D | 1330 | 12 Jan 2002 | 0.50 |
|
0.50 | Reenter Hole 1224D at 1336 hr |
|
Run in hole, space out to land casing | 1515 | 12 Jan 2002 | 1.75 |
|
1.75 |
Land 10![]() |
|
Cement with 18.8 bbl of 15.5 ppg | 1645 | 12 Jan 2002 | 1.50 |
|
1.50 | Release dart at 1635 hr |
|
|
|
|
|
|
|
Bump plug with 900 psi; no flowback |
|
Release running tool from casing | 1715 | 12 Jan 2002 | 0.50 |
|
0.50 | Release on second attempt at 1715 hr |
|
Recover VIT | 2000 | 12 Jan 2002 | 2.75 |
|
2.75 |
|
|
Slip and cut drill line | 2115 | 12 Jan 2002 | 1.25 |
|
1.25 | Clear seafloor at 1715 hr |
|
Pull out of hole | 0600 | 13 Jan 2002 | 8.75 |
|
8.75 | Clear rotary at 0530 hr |
|
Make up BHA and run in hole | 1600 | 13 Jan 2002 | 10.00 |
|
10.00 | Clean out Hole 1224D inside casing |
|
Reenter Hole 1224D | 1630 | 13 Jan 2002 | 0.50 |
|
0.50 | Reenter Hole 1224D at 1630 hr |
|
|
|
|
|
|
|
Reentry cone sank 1.75 m |
|
Wash out soft cement | 1715 | 13 Jan 2002 | 0.75 |
|
0.75 | 54.6-58.1 mbsf |
|
Circulate casing clean | 1745 | 13 Jan 2002 | 0.50 |
|
0.50 | Science objective obtained |
|
Pull out of hole | 1815 | 13 Jan 2002 | 0.50 |
|
0.50 | Clear seafloor at 1817 hr |
|
|
|
|
|
Total: | 253.50 |
|
|
Hole 1224D waiting on weather |
|
|
|
|
97.50 |
|
|
|
|
|
|
|
|
|
1224E | Offset 15 m southwest | 1845 | 13 Jan 2002 | 0.50 |
|
0.50 |
|
|
Tag seafloor at 4978 mbrf | 1900 | 13 Jan 2002 | 0.25 |
|
0.25 | Tag seafloor at 1840 hr |
|
Wash, punch Cores 1R and 2R | 2215 | 13 Jan 2002 | 3.25 |
|
3.25 | 0-8 mbsf; 8-27.1 mbsf |
|
3R, 27.1-36.7 mbsf | 1500 | 14 Jan 2002 | 16.75 |
|
16.75 | Tag hard at 27.7 mbsf |
|
Cleared seafloor | 1500 | 14 Jan 2002 | 0.00 |
|
0.00 | Pulled out of basement |
|
|
|
|
|
Total: | 20.75 |
|
1224F | Looking for Hole 1224E | 1630 | 14 Jan 2002 | 1.50 |
|
1.50 | Pulled out of basement as pulled out of hole |
|
Spud hole | 1630 | 14 Jan 2002 |
|
|
|
|
|
Core 1R, 27.7-39.70 mbsf | 0455 | 15 Jan 2002 | 12.42 |
|
12.42 | New hole with bare rock spud |
|
Cores 2R-4R, 39.70-65.90 mbsf | 0650 | 16 Jan 2002 | 25.92 |
|
25.92 | Flow basalt and high recovery |
|
|
|
|
|
|
|
Drilling break 62.7 mbsf, Hole 1224D |
|
Cores 5R-11R, 65.9-128.50 mbsf | 2315 | 17 Jan 2002 | 40.42 |
|
40.42 | Altered basalt poor recovery |
|
Short trip for knobbies | 0115 | 18 Jan 2002 | 2.00 |
|
2.00 | Pull out of hole above basement contact |
|
Search for and reenter Hole F | 0200 | 18 Jan 2002 | 0.75 |
|
0.75 |
|
|
Run in hole from 25.69-93.16 mbsf | 0330 | 18 Jan 2002 | 1.50 |
|
1.50 |
|
|
TSF mechanical breakdown | 0700 | 18 Jan 2002 | 3.50 |
|
3.50 | Repack swivel on top drive |
|
Run in hole from 93.16-128.5 mbsf | 0830 | 18 Jan 2002 | 1.50 |
|
1.50 | 12-m soft fill circulated out |
|
Cores 12R-14R, 128.5-143 mbsf | 1700 | 18 Jan 2002 | 8.50 |
|
8.50 | 3-m fill on Core 14R |
|
Work pipe to clean hole | 1745 | 18 Jan 2002 | 0.75 |
|
0.75 | 400 amp and 4-m fill |
|
Cores 14R-16R, 143-171 mbsf | 1700 | 19 Jan 2002 | 23.25 |
|
23.25 | Zero recovery Core 16R |
|
Run bit deplugger | 2015 | 19 Jan 2002 | 3.25 |
|
3.25 | Did not appear to seat in bit |
|
Core 17R, 171-174.5 mbsf | 2245 | 19 Jan 2002 | 2.50 |
|
2.50 | Zero recovery Core 17R |
|
Run in hole with rotary shifter tool | 0000 | 20 Jan 2002 | 1.25 |
|
1.25 | Drop bit at 2320 hr |
|
Displace hole for logging | 0045 | 20 Jan 2002 | 0.75 |
|
0.75 |
|
|
Pull out of hole for logging | 0230 | 20 Jan 2002 | 1.75 |
|
1.75 | EOP 49.94 mbsf |
|
Drop FFF | 0515 | 20 Jan 2002 | 2.75 |
|
2.75 |
|
|
Rig up and run log 1 | 1615 | 20 Jan 2002 | 11.00 |
|
11.00 | DITE/HLDT/APS/HNGS |
|
|
|
|
|
|
|
In at 0745 hr, depth 5152 m; out at 1520 hr |
|
Rig up and run log 2 | 1945 | 20 Jan 2002 | 3.50 |
|
3.50 | FMS/NGT/DSI |
|
|
|
|
|
|
|
Misrun replace telemetry tool |
|
Log 2 in | 1945 | 20 Jan 2002 | 0.00 |
|
0.00 | Depth 5152 m (174 mbsf) |
|
Log 2 out | 0530 | 21 Jan 2002 | 9.75 |
|
9.75 | Out at 0525 hr |
|
Rig up and run log 3 | 0945 | 21 Jan 2002 | 4.25 |
|
4.25 | WST in; 0745 hr misrun |
|
|
|
|
|
|
|
Depth 1057 m, out at 0945 hr |
|
Rig down logging | 1030 | 21 Jan 2002 | 0.75 |
|
0.75 |
|
|
Pull upper guide horn and launch VIT | 1100 | 21 Jan 2002 | 0.50 |
|
0.50 |
|
|
Run in hole with VIT to observe FFF | 1230 | 21 Jan 2002 | 1.50 |
|
1.50 | Observe FFF at 1225 hr |
|
Clear seafloor | 1238 | 21 Jan 2002 | 0.13 |
|
0.13 |
|
|
Pull out of hole with DP and VIT | 1415 | 21 Jan 2002 | 1.62 |
|
1.62 |
|
|
Recover VIT | 1500 | 21 Jan 2002 | 0.75 |
|
0.75 |
|
|
1st beacon on deck | 1612 | 21 Jan 2002 |
|
|
|
|
|
2nd beacon on deck | 1800 | 21 Jan 2002 |
|
|
|
|
|
Pull out of hole with DP to 112.92 mbrf | 2115 | 21 Jan 2002 | 6.25 |
|
6.25 |
|
|
MBR clear rotary | 2355 | 21 Jan 2002 |
|
|
|
|
|
Lay out DC to catwalk | 0000 | 22 Jan 2002 | 2.75 |
|
2.75 |
|
|
Secure ship for sea voyage | 0030 | 22 Jan 2002 | 0.50 |
|
0.50 | Depart site at 0030 hr |
|
Seismic survey over H2O-5 (Site 1224) | 0145 | 22 Jan 2002 | 1.25 |
|
1.25 | Functional test |
|
|
|
|
|
Total: | 178.75 |
|
|
|
|
|
|
|
|
|
|
Hole 1224F |
|
|
|
|
|
|
|
TSF mechanical downtime |
|
|
|
|
3.50 |
|
|
LDEO logging downtime |
|
|
|
|
7.75 |
|
|
ODP mechanical downtime |
|
|
|
|
0.00 |
|
H2O-5 (Site 1224) | Depart site | 0145 | 22 Jan 2002 |
|
|
|
|
San Diego | End of sea voyage (pilot aboard) | 0700 | 27 Jan 2002 | 125.25 |
|
125.25 | Traveled 1320 nmi at 10.49 kt |
|
First line ashore | 0820 | 27 Jan 2002 |
|
|
1.33 |
|
|
|
|
|
|
Total: | 126.58 |
|
|
|
Total hours: |
|
|
779.68 |
|
|
|
|
Total days: |
|
|
32.49 |
|
Note: GPS = global positioning system, DP = drill pipe, VIT = vibration isolated television, APC = advanced piston corer, BHA = bottom-hole assembly, CHRT = casing hanger running tool, RCB = rotary core barrel, TD = total depth, AHC = active heave compensator, EOP = end of pipe, FFF = free-fall funnel, DITE = Digital Dual Induction Tool model E, HLDT = Hostile Environment Litho-Density Tool, APS = accelerator porosity sonde, HNGS = Hostile Environment Natural Gamma Ray Sonde, FMS = Formation MicroScanner, NGT = Natural Gamma Spectrometry Tool, DSI = Dipole Sonic Imager, WST = Well Seismic Tool, DC = drill collar, MBR = mechanical bit release, TSF = Transocean Sedco Forex.