Table T1. Coring summary, Site 1225.
Hole 1225A
Latitude: 2°46.2469´N
Longitude: 110°34.2889´W
Time on site (hr): 132.25 (2125 hr, 7 Feb-0930 hr, 13 Feb 2002)
Time on hole (hr): 86.00 (2115 hr, 7 Feb-1115, 11 Feb 2002)
Seafloor (drill pipe measurement from rig floor, mbrf): 3772.20
Distance between rig floor and sea level (m): 10.90
Water depth (drill pipe measurement from sea level, m): 3761.30
Total depth (drill pipe measurement from rig floor, mbrf): 4091.80
Total penetration (meters below seafloor, mbsf): 319.60
Total length of cored section (m): 315.60
Total length of drilled intervals (m): 4.00
Total core recovered (m): 321.65
Core recovery (%): 101.92
Total number of cores: 35
Total number of drilled intervals: 3
Hole 1225B
Latitude: 2°46.2526´N
Longitude: 110°34.2891´W
Time on hole (hr): 2.00 (1115 hr, 11 Feb-1315 hr, 11 Feb 2002)
Seafloor (drill pipe measurement from rig floor, mbrf): 3771.0
Distance between rig floor and sea level (m): 10.9
Water depth (drill pipe measurement from sea level, m): 3760.1
Total depth (drill pipe measurement from rig floor, mbrf): 3780.0
Total penetration (meters below seafloor, mbsf): 9.0
Total length of cored section (m): 9.0
Total length of drilled intervals (m): 0.0
Total core recovered (m): 8.96
Core recovery (%): 99.6
Total number of cores: 1
Total number of drilled intervals: 0
Hole 1225C
Latitude: 2°46.2572´N
Longitude: 110°34.2890´W
Time on hole (hr): 44.25 (1315 hr, 11 Feb-0930 hr, 13 Feb 2002)
Seafloor (drill pipe measurement from rig floor, mbrf): 3771.2
Distance between rig floor and sea level (m): 11.0
Water depth (drill pipe measurement from sea level, m): 3760.2
Total depth (drill pipe measurement from rig floor, mbrf): 4076.5
Total penetration (mbsf): 305.3
Total length of cored section (m): 304.3
Total length of drilled intervals (m): 1.0
Total core recovered (m): 305.51
Core recovery (%): 100.4
Total number of cores: 33
Total number of drilled intervals: 1
Core
Date
(Feb 2002)
Local time
(hr)
Depth (mbsf)
Length (m)
Recovery (%)
Top
Bottom
Cored
Recovered
201-1225A-





1H 8 0900 0.0 4.3 4.3 4.29 99.8
2H 8 1015 4.3 13.8 9.5 10.03 105.6
3H 8 1120 13.8 23.3 9.5 9.85 103.7
4H 8 1230 23.3 32.8 9.5 9.81 103.3
5H 8 1415 32.8 42.3 9.5 10.16 107.0
6H 8 1525 42.3 51.8 9.5 10.11 106.4
7H 8 1705 51.8 61.3 9.5 9.95 104.7
8H 8 1815 61.3 70.8 9.5 10.01 105.4
9H 8 1945 70.8 80.3 9.5 10.02 105.5
10H 8 2050 80.3 89.8 9.5 10.06 105.9
11H 8 2155 89.8 99.3 9.5 10.01 105.4
12H 8 2300 99.3 108.8 9.5 9.96 104.8
13H 9 0010 108.8 118.3 9.5 10.03 105.6
14H 9 0150 118.3 127.8 9.5 10.23 107.7
15H 9 0310 127.8 137.3 9.5 9.98 105.1
16H 9 0415 137.3 146.8 9.5 10.23 107.7
17H 9 0540 146.8 156.3 9.5 9.56 100.6
18H 9 0655 156.3 165.8 9.5 9.78 103.0
19H 9 0800 165.8 175.3 9.5 9.98 105.1
20H 9 0925 175.3 184.8 9.5 9.96 104.8
21H 9 1025 184.8 194.3 9.5 9.62 101.3
22H 9 1145 194.3 203.8 9.5 9.96 104.8



*****Drilled from 203.8 to 205.3 mbsf*****
23H 9 1715 205.3 214.8 9.5 10.11 106.4
24H 9 1835 214.8 224.3 9.5 10.05 105.8
25H 9 1950 224.3 233.8 9.5 10.03 105.6
26H 9 2135 233.8 243.3 9.5 10.02 105.5
27H 9 2325 243.3 252.8 9.5 10.13 106.6
28X 10 0330 252.8 262.2 9.4 0.00 0.0
29P 10 0530 262.2 263.2 1.0 1.41 141.0



*****Drilled from 263.2 to 264.2 mbsf*****
30H 10 0725 264.2 273.7 9.5 8.79 92.5
31H 10 0905 273.7 283.2 9.5 10.12 106.5
32H 10 1050 283.2 292.7 9.5 10.00 105.3
33H 10 1230 292.7 302.2 9.5 10.03 105.6



*****Drilled from 302.2 to 303.7 mbsf*****
34H 10 1745 303.7 313.2 9.5 10.12 106.5
35X 10 1925 313.2 319.6 6.4 7.25 113.3



Cored totals: 315.6 321.65 101.9



Drilled total: 4.0





Total: 319.6

201-1225B-





1H 11 1310 0.0 9.0 9.0 8.96 99.6



Cored totals: 9.0 8.96 99.6
201-1225C-





1H 11 1415 0.0 8.8 8.8 8.79 99.9
2H 11 1510 8.8 18.3 9.5 9.96 104.8
3H 11 1630 18.3 27.8 9.5 10.04 105.7
4H 11 1720 27.8 37.3 9.5 10.01 105.4
5H 11 1840 37.3 46.8 9.5 9.31 98.0
6H 11 1935 46.8 56.3 9.5 10.02 105.5
7H 11 2035 56.3 65.8 9.5 9.84 103.6
8H 11 2135 65.8 75.3 9.5 10.02 105.5
9H 11 2230 75.3 84.8 9.5 9.87 103.9
10H 11 2325 84.8 94.3 9.5 9.73 102.4
11H 12 0025 94.3 103.8 9.5 9.91 104.3
12H 12 0125 103.8 113.3 9.5 9.64 101.5
13H 12 0220 113.3 122.8 9.5 9.84 103.6
14H 12 0320 122.8 132.3 9.5 9.83 103.5
15H 12 0415 132.3 141.8 9.5 9.80 103.2
16H 12 0525 141.8 151.3 9.5 10.05 105.8
17H 12 0700 151.3 160.8 9.5 9.52 100.2
18H 12 0800 160.8 170.3 9.5 9.66 101.7
19H 12 0900 170.3 179.8 9.5 9.86 103.8
20H 12 0950 179.8 189.3 9.5 9.13 96.1
21H 12 1055 189.3 198.8 9.5 9.70 102.1
22H 12 1200 198.8 208.3 9.5 9.65 101.6
23H 12 1325 208.3 217.8 9.5 9.89 104.1
24H 12 1445 217.8 227.3 9.5 10.02 105.5
25H 12 1645 227.3 236.8 9.5 9.95 104.7
26H 12 1830 236.8 246.3 9.5 10.08 106.1
27H 12 1940 246.3 255.8 9.5 10.06 105.9
28H 12 2110 255.8 265.3 9.5 10.08 106.1
29H 12 2230 265.3 274.8 9.5 6.86 72.2
30H 13 0005 274.8 284.3 9.5 10.04 105.7
31H 13 0145 284.3 293.8 9.5 10.09 106.2
32P 13 0330 293.8 294.8 1.0 1.02 102.0



*****Drilled from 294.8 to 295.8 mbsf*****
33H 13 1845 295.8 305.3 9.5 3.24 34.1



Cored totals: 304.3 305.51 100.4



Drilled total: 1.0





Total: 305.3