Date
(Aug 2002) |
Local time
(hr) |
Tool depth (mbsf)
|
Remarks
|
---|---|---|---|
23 | 1145 |
|
Last core on deck |
23 | 1145-1415 |
|
Wiper trip up to 80 mbsf; back down to 220 mbsf |
23 | 1415-1430 |
|
Hole displaced with sepiolite mud |
23 | 1430-1530 |
|
Set back top drive; bottom of pipe put at 90 mbsf |
23 | 1635 |
|
Start logging rig up |
23 | 1755 |
|
Start going down with the triple combination (TAP/DIT/HLDT/APS/HNGS/QSST) tool string |
23 | 1845 | 0 | Stop 5 min at mudline for temperature calibration |
23 | 1900 | 220 | Tool at TD; start logging-up pass at 900 ft/hr |
23 | 1925 | 74 | Tool back into pipe; speed up to 1500 ft/hr to log mudline |
23 | 1935 | 0 | End of pass 1 |
23 | 1952 | 204 | Tool at TD; start logging-up pass 2 at 900 ft/hr |
23 | 2022 | 73 | Tool back in pipe; end of pass 2 |
23 | 2032 | 220 | Tool at TD for QSST checkshot survey |
23 | 2110 | 74 | Tool back into pipe |
23 | 2150 |
|
Tool back on rig floor |
23 | 2315 |
|
Finish rig-down |
23 | 2315 |
|
Start logging rig up |
24 | 0020 |
|
Start going down with FMS-sonic (FMS/DSI/SGT) tool string |
24 | 0100 | 220 | Tool at TD; start logging-up pass at 900 ft/hr |
24 | 0135 | 73 | Tool back into pipe; end of pass 1 |
24 | 0145 | 220 | Tool at TD; start logging-up pass 2 at 900 ft/hr |
24 | 0210 | 73 | High tension when top of tool enters pipe; end of pass 2 |
24 | 0245 | 73 | Tool worked into pipe |
24 | 0320 |
|
Tool back on rig floor |
24 | 0415 |
|
Finish rig-down |
Notes: TD = total depth. See Table T8 in the "Explanatory Notes" chapter for definitions of acronyms.