166 Preliminary Report


Operations Resume

Total Days (17 February to 10 April 1996)		52.72
Total Days in Port (Repairs)				4.63
Total Days Underway					6.80
Total Days on Site					41.29
	Tripping Time				3.77
	Coring					24.39
	Reentry Time				0.00
	W.O.W.					0.00
	Stuck pipe/Hole trouble			0.000
	Drilling				4.16
	Mechanical Repair Time (Contractor)	0.00
	Logging/Downhole Science		6.83
	Other					0.20
Total Distance Travelled (nautical miles)		2045.0
Average Speed Transit (knots)				11.9
Number of Sites						7
Number of Holes						17
Number of Cores Attempted				572
Total Interval Cored (m)				5254.9
Total Core Recovery (m)					2933.8
% Core Recovery						55.8
Total Interval Drilled (m)				2197.5
Total Penetration					7452.4
Maximum Penetration (m)					1300.0
Minimum Penetration (m)					6.6
Maximum Water Depth (m from drilling datum)		669.9
Minimum Water Depth (m from drilling datum)		319.7