OPERATIONS REPORT
The drilling and engineering personnel aboard the JOIDES Resolution for Leg 174A were:
Operations Manager | Gene Pollard |
Operations Engineer | Brian Jonasson |
Schlumberger Engineer | Steve Kittredge |
Anadrill Engineer | Thomas Horton |
TRANSIT TO SITE 1071
The vessel departed Halifax at 1812 hr on Friday, 20 June, 1997. The 578-nmi transit to Site 1071
was accomplished at an average speed of 10.8 kt. The vessel arrived on location at 2330 hr on
22 June, 1997. All times reported are in local time (U.S. Eastern Time Zone; UTC = 4 hr).