OPERATIONS SYNOPSIS
Site 1174
The PDR indicated a water depth of 4754.4 mbrf. An eight-drill collar
APC/XCB BHA was made up with an 11-7/16-in roller cone bit, LFV, a seal
bore drill collar, landing saver sub, top sub, head sub, nonmagnetic drill collar,
five 8-1/4-in drill collars, one TDC, six joints of 5-1/2-in drill pipe, and a
crossover sub to 5-in drill pipe. The drill string was tripped to the seafloor,
the bit was positioned at 4741.1 mbsl (4752.4 mbrf), and core was taken
but did not recover any sediment. The bit was repositioned at 4746.1 mbsl
(4757.4 mbrf) and Hole 1174A was successfully spudded at 1735 hr on 7
June. Core 1H recovered 4.4 m of sediment, establishing the drilling depth as
4751.2 mbsl (4762.5 mbrf).
Hole 1174A
Cores 1H to 8H were cored from 0 to 64.4 mbsf and recovered 47.04 m
(73%). Fine-grained sand and silts likely caused the somewhat low core
recovery. The force required to pull the APC barrel out of the formation
increased until it had reached 70,000 lb on Core 7H. Core 8H resulted in a
partial stroke with only 3 m of penetration, so the coring system was
changed over to the XCB.
Core 9X was cut from 64.4 to 74.1 mbsf. When we tried to retrieve the
core barrel, it could not be pulled free from the BHA. A 50-bbl sepiolite pill
was pumped past the core barrel in an effort to clean any sands/silts that
might be causing it to jam, but this did not help and the entire drill string had
to be recovered. The bit cleared the rotary table at 0130 hr on 9 June,
officially ending Hole 1174A.
When the BHA reached the rig floor, it was discovered that the core
barrel was stuck inside the nonmagnetic outer drill collar. When the core
barrel was finally dislodged, one of the XCB latching mechanisms (dogs) was
found to have failed. A 1-1/2-in long piece was missing from the middle of the
latch dog. One of the remaining ends of the latch was still locked inside the
XCB body and had rotated outward, pinning the core barrel in place. This is
the first known occurrence of this type of failure, and the cause is as yet
unknown.
Hole 1174B
The decision was made to set a drill-in-casing (DIC) system in Hole 1174B
to case off the loose sands near the seafloor in preparation for an 1150-m
deep penetration through the protothrust and décollement zones. Eleven
joints of 11-3/4-in casing (142.2 m) were made up with a new 14-3/4-in
sawtooth casing bit welded on the end and hung off on the moonpool doors. A
9-7/8-in tri-cone bit was made up to the drilling assembly and was spaced out
~1 m ahead of the casing bit. Once the drilling assembly was attached to the
casing assembly, a DIC reentry funnel was attached to the DIC drive bushing.
The completed DIC assembly was then lowered to the seafloor.
While we assembled the DIC system, it was necessary to allow the ship to
drift with the current. After the DIC assembly had reached the seafloor,
another hour of maneuvering in DP mode was required to move the vessel
back on location. Hole 1174B was spudded at 0943 hr on 10 June.
The DIC was first jetted into ~50 mbsf with the following maximum jetting
parameters, 45 strokes per minute (spm), 400 psi, 510 klbs weight on bit
(WOB). Then the DIC was drilled into 143.67 mbsf (4906.17 mbrf) with
maximum drilling parameters of 80 spm, 1050 psi, 810 klbs WOB, 10 rpm,
and 60009000 ft-lb of torque. Total time for emplacement was ~7.25 hr,
and no problems were encountered.
The rotary shifting tool (RST) was then deployed on the wireline to unlatch
the DIC. The weight of the DIC casing, ~22,000 lb, was slacked off in
preparation for unlatching. The RST had to be worked through the DIC three
times before a definite indication of the release sleeve shifting was
observed. The drill string was then picked up, and the weight of the DIC
system was lost, indicating that it had released properly.
We intended to have Hole 1174B penetrate a relatively thick section that
might be unstable; therefore, the decision was made to round trip the drill
string to remove the DIC drive sub and then reenter with a standard RCB
BHA. Thus, the drill string was recovered.
The DIC BHA was broken out, and an RCB BHA was made up. The RCB was
tripped to the seafloor and the vibration-isolated television (VIT) camera
frame was lowered to the seafloor in preparation for reentry. The search for
the DIC reentry funnel began at 1830 hr on 11 June, and the funnel was first
sighted visually at ~2315 hr. At 2347 hr on 11 June, Hole 1174B was
reentered and the VIT was recovered. The bit was lowered into the hole with
moderate drag until the bit had reached 52.5 mbsf, where some resistance
was encountered. The top drive was picked up, and the bit had to be worked
down all the way through the cased section.
Hole 1174B was then cored from 143.7 to 265.8 mbsf (4906.2 to 5028.3
mbrf) with high erratic torque. At this depth the bit became stuck. The drill
string was worked for 1 hr, and 120,000 lb of overpull was required to free
the bit. The bit was raised up inside the casing with drag and high erratic
torque all the way. The bit was eventually raised to 50 mbsf (4852 mbrf),
where the high erratic torque finally disappeared.
The bit was lowered once again, encountering an obstruction at 52.5 mbsf
(4854.5 mbrf). The bit was worked through this problem area inside the
casing several times until it was thought that the obstruction was no longer
a threat to the coring operations. The bit was then lowered back down into
the open hole, encountering fill at 172.5 mbsf (4935 mbrf). The hole was
washed and reamed to bottom and coring resumed.
Some further insight into the mysterious high erratic torque previously
observed while coring in Hole 1174B appeared in the top of Core 20R. A piece
of chewed-up metal ~3 in long, 1-1/2 in wide, and 1/4 in thick was recovered.
Additional pieces of metal were found in other succeeding cores.
Unfortunately, the origin of the metal is still not clear.
While retrieving Core 40R from 524.3 mbsf (5286.8 mbrf), the forward
core winch wireline parted at the crown with the core barrel at 3664 mbrf.
The frayed end of the wireline caught in the oil saver on top of the swivel and
T-bar clamps were used to pull the parted wireline up through the top drive.
Preparations were then made to string the parted wireline back over the
crown sheave and reattach it to the coring winch. However, when the derrick
man reached the crown, he discovered that the outboard wireline crown
sheave had failed.
Approximately one-third of the sheave rim on the outboard side had
separated from the sheave body. A used sheave was located on board and
was installed to replace the failed sheave.
The parted wireline was strung over the replacement sheave and reattached
to the core winch with cable clamps. The parted wireline was recovered along
with the core barrel, which contained 9.21 m of core. The forward core winch
was secured, and the aft core winch, which had 9600 m of new wireline on it,
was placed into service. A total of 8.25 hr of down time was incurred as a
result of the parted wireline and failed sheave.
Although rotation and circulation were maintained while we recovered the
parted wireline and replaced the failed sheave, a wiper trip was carried out
before we resumed coring operations. The bit was pulled to 128.43 mbsf
(4890.93 mbrf), inside the DIC casing shoe. Once the bit was back inside the
casing, an overdue maintenance of the drill line (slip and cut) was carried out.
The bit was then lowered to 459.86 mbsf (5222.36 mbrf), where slight drag
was encountered. The top drive was picked up and the hole was washed and
reamed to 524.3 mbsf. Approximately 7 m of soft fill was encountered in
the bottom of the hole. RCB coring then resumed, and Cores 41R to 102R
were recovered from 533.9 to 1119.8 mbsf (5882.3 mbrf). After drilling in
the DIC to 143.7 mbsf, Hole 1174B was continuously cored through 976.1 m
of section. Recovery was 577.57 m (60%).
Because some gas was detected in the formation, the hole was displaced
with 280 bbl of heavy mud. After the hole was displaced, the pipe was pulled
out of the hole with no rotation or circulation. When the bit reached 398.2
mbsf (5160.3 mbrf), a tight spot was encountered and the pipe was worked
without picking up the top drive. A 60,000-lb overpull was being applied to
the drill string when the pipe came free. However, the drill string weight was
~70,000 lb lighter, indicating that the drill string had parted, and the pipe
trip continued. The drill string had parted 467 m above the seafloor.
Once the drill pipe was clear of the seafloor, the two seafloor positioning
beacons were given release commands. The primary beacon released and was
recovered. However, the backup beacon failed to release and was not
recovered. Once the beacon was on board and the end of the pipe was near
the rig floor, the thrusters and hydrophones were raised and the vessel
began the 2-hr transit to Site ENT-05A (1175).
The end of the drill pipe cleared the rig floor at 2230 hr on 22 June. The
pin connection on the bottom of drill pipe stand number 26 had failed. Lost in
the hole were a 97a -in RCB bit, mechanical bit release, outer core barrel, top
sub, head sub, seven 8-1/4-in drill collars, transition drill collar, six joints of
5-1/2-in drill pipe, a crossover sub, and 75 joints of 5-in drill pipe.