OPERATIONS SYNOPSIS
Hole 1178A
Because of the strong current, the ship had to be offset upcurrent from
the location and allowed to drift back to enable the drill collars to be made
up. A BHA consisting of a 9-7/8-in PDC bit, bit sub, seal bore drill collar,
landing saver sub, modified top sub, modified head sub, nonmagnetic drill
collar, seven 8-1/4-in drill collars, a tapered drill collar, and crossover sub was
assembled.
A PDR measurement was taken that indicated a drilling depth of 1716.5
mbsl (1728.4 mbrf). The bit was lowered to 1710 mbrf where a bottom
water sample was collected using the WSTP. The bit was then lowered to
1728 mbrf; core was taken but no sediment was recovered. The bit was
lowered to 1725.6 mbsl (1737.5 mbrf), and another core was taken, with no
sediment recovered. The bit was once again lowered 9.5 m to 1735.1 mbsl
(1747 mbrf), and Hole 1178A was spudded at 1855 hr on 8 July. Core 1H
recovered 2.9 m of sediment, establishing the seafloor depth as 1741.7
mbsl (1753.6 mbrf).
Cores 1H to 44X were taken from 0 to 410.8 mbsf (1753.62164.4
mbrf), recovering 340.19 m of core (83%). The penetration rate had
decreased to <6 m/hr, when the decision was made to terminate XCB coring
and switch to RCB coring. Hole 1178A was filled with 122 bbl of heavy mud,
and then the pipe was tripped out of the hole. The bit cleared the rig floor at
1430 hr on 11 July, officially ending Hole 1178A. Because Hole 1178A was
the last deployment of the APC/XCB BHA for Leg 190, it was disassembled.
Hole 1178B
The ship was offset 20 m to the east as an RCB BHA was being
assembled. The BHA consisted of a new 9-7/8-in CC-3 roller cone bit, a bit
sub, 8-1/4-in drill collar, modified top sub, modified head sub, seven 8-1/4-in drill
collars, a tapered drill collar, six joints of 5-1/2-in drill pipe, and a crossover
sub to 5-in drill pipe. The bit was tripped to the seafloor, and Hole 1178B was
spudded at 2015 hr on 11 July.
Hole 1178B was first drilled to 395 mbsf (1753.62148.6 mbrf). RCB
coring then commenced, and Cores 2R through 31R were taken from 395.0
to 679.2 mbsf (2148.62432.8 mbrf), recovering 165.96 m of core (58%).
During operations at Site 1178, the current generally averaged between
2.5 and 3.5 nmi/hr. However, on several occasions it was believed that the
current was over 5 nmi/hr. The bridge speed log indicated 4.8 nmi/hr during
those times, and 100 turns on both screws were required to maintain
station. Severe vibrations in the drill string were observed. The vibrations
were transmitted up to the top drive and associated traveling equipment.
The electrical supervisor reported that the hydrophones were vibrating
severely within their wells. The aft side of the upper guide horn was too hot
to touch with a bare hand because of the drill string rubbing against it.
Even though the ship was able to maintain position during the peak current
times, we thought that the safe operational limits had been reached for two
reasons. First, the automatic station keeping (ASK) system was already
operating at its maximum output available from the main screws. Any
increase in the 1012 nmi/hr head winds would have exceeded the ASK
systems ability to maintain station. Second, and perhaps more importantly,
the severe vibration in the drill string and traveling equipment was of great
concern. Fatiguing of drill-pipe connections as well as possible damage to
compensator rods and seals was a distinct possibility. There were also
concerns about any loose objects that might fall out of the derrick. Had the
current increased above the perceived 5 nmi/hr, operations would have had
to be shut down.
At 1515 hr on 12 July, three thrusters (T-2, T-4, and T-5) automatically
tripped off line. Fortunately the ASK system was able to compensate for the
lost thrusters and maintain ship position. With a 3+ nmi/hr current running
at the time, the decision was made to raise the bit from the current total
depth of the hole (419.3 mbsf) to 32.7 mbsf until the ASK system problem
could be resolved. The problem was traced to a faulty transformer in the
forward thyrig room. This transformer supplied power to the thruster
controller cards and was giving a faulty signal. The transformer was
bypassed, and the ASK system performance immediately returned to normal.
Operations were resumed after losing 4.5 hr.
Coring was stopped in Hole 1178B when the allotted coring time for Leg
190 expired at 0600 hr on 15 July. The hole was filled with heavy mud and
the bit was tripped out. The bit cleared the seafloor at 0845 hr, and the
positioning beacon was released and recovered at 1045 hr. The bit cleared
the rig floor at 1250 hr on 15 July, officially ending Hole 1178B and
operations at Site 1178.
Transit from Site 1178 to Yokohama
The ship began the transit to Yokohama at 1400 hr on 15 July. The first
line was ashore at 1600 hr on 16 July at Daikoku Wharf, Yokohama, Japan,
officially ending Leg 190.