Table 1. Chronologic operations summary.

Date   Location Task
Start Finish      
(2000) (2000)      
         
7 Nov 14 Nov   Port call  
14 Nov 18 Nov   Transit  
18 Nov 22 Nov   Hole 1188A RCB coring
22 Nov 23 Nov   Hole 1189A RCB coring
23 Nov 25 Nov   Holes 1190A, 1190B, 1190C RCB coring
25 Nov 27 Nov   Hole 1188B RAB/LWD/ADCB
27 Nov 28 Nov   Site 1191 RCB coring
28 Nov 1 Dec   Holes 1188C, 1188D, 1188E No coring
1 Dec 12 Dec   Hole 1188F Casing
12 Dec 21 Dec   Hole 1188F ADCB coring/logging
21 Dec 22 Dec   Hole 1188F Water-sampling/temperature measurements
22 Dec 26 Dec   Hole 1189B HRRS casing/RCB coring/logging
27 Dec 29 Dec   Hole 1189C, Hole 1188F RAB/LWD/ logging, temperature measurements/water sampling

Note:
RCB = rotary core barrel, RAB = resistivity at bit, LWD = logging while drilling
ADCB = advanced diamond core barrel, HRRS = hard-rock reentry system.