Table T3. Operations conducted during Leg 206.

Hole
Activity
Time (local)
Date (2002)
Operation on hole
Time
on hole (hr)
Time
on site (hr)
Time on site
(days)
Comments
1256A
On location with GPS
1630
Nov 14




Spud at 0640 hr on 15 Nov

Clear seafloor 1256A
0645
Nov 15

14.25
14.25
0.59
Objective attained
1256B
Clear seafloor 1256A
0645
Nov 15




Spud at 0815 hr on 15 Nov

Bit at rotary table
0630
Nov 17

47.75
62.00
2.58
Basement reached
1256C
Bit at rotary table
0630
Nov 17




Spud at 1515 hr on 17 Nov

EOP at rotary table
0345
Nov 23

141.25
203.25
8.47
Depth objective attained
1256D
EOP at rotary table
0345
Nov 23
Jet-in 20-in casing



Spud reentry cone and casing


1035
Nov 24
End jetting
30.83
234.08
9.75
Reach 95 mbsf; release CADA


2015
Nov 24
Bit at rotary table
9.67
243.75
10.16
Change to bi-reamer BHA


0620
Nov 25
Reentry 1
10.08
253.83
10.58
Enter cone with bi-reamer BHA


0815
Nov 25
Begin drilling
1.92
255.75
10.66
Start 21.5-in hole at 95 mbsf


0445
Nov 27
End drilling
44.50
300.25
12.51
Stop at ~17 m into basement


1300
Nov 27
Bit at rotary table
8.25
308.50
12.85
Failed bit bearing put junk in hole


2140
Nov 27
Reentry 2
8.67
317.17
13.22
Reenter with 2X junk basket BHA


0000
Nov 28
Start cleaning
2.33
319.50
13.31
Work junk baskets


0330
Nov 28
End cleaning
3.50
323.00
13.46
Advance 1 m into basement


0505
Nov 28
Clear seafloor
1.58
324.58
13.52
Recover drill string


1140
Nov 28
Bit at rotary table
6.58
331.17
13.80
Change to bi-reamer BHA


1755
Nov 28
Reentry 3
6.25
337.42
14.06
Enter cone with bi-reamer BHA


2000
Nov 28
Begin drilling
2.08
339.50
14.15
Resume 21.5-in hole at ~17 m in basement


0030
Nov 30
Begin wiper trip
28.50
368.00
15.33
TD hole at 276.1 mbsf (26.1 m in basement)


0415
Nov 30
Displace hole
3.75
371.75
15.49
150 bbl sepiolite; 100 bbl barite


0700
Nov 30
Clear seafloor
2.75
374.50
15.60
Recover drill string


1330
Nov 30
Bit at rotary table
6.50
381.00
15.88
Rig-up for 16-in casing


0417
Dec 1
Casing wet at 0417 hr
14.78
395.78
16.49
End making up casing


1040
Dec 1
Detect crushed joint
6.38
402.17
16.76
Stop running casing


0004
Dec 2
Recover casing
13.40
415.57
17.32
Replace four joints and casing collar


1135
Dec 2
Casing wet at 1135 hr
11.52
427.08
17.80
End repair of casing string


2008
Dec 2
Reentry 4
8.55
435.63
18.15
Weather getting bad; heave = ~2.5 m


2315
Dec 2
Clear seafloor
3.12
438.75
18.28
POOH due to heave = ~4 m


0650
Dec 3
Reentry 5
7.58
446.33
18.60
WOW for 5.75 hr


1730
Dec 3
Land casing
10.67
457.00
19.04
Work stuck casing for 3.75 hr


1745
Dec 3
Cement casing
0.25
457.25
19.05
30 bbl cement


2115
Dec 3
Clear seafloor
3.50
460.75
19.20
Release CADA running tool


0500
Dec 4
CADA tool on surface
7.75
468.50
19.52
Detorque CADA tool


0630
Dec 4
Begin to run in hole
1.50
470.00
19.58
Make up bit 1: CC4 SN BX-020


1500
Dec 4
Reentry 6
8.50
478.50
19.94
Quick reentry


1815
Dec 4
Start to drill cement
3.25
481.75
20.07
Attempted core/dropped chisel


0955
Dec 5
Clear seafloor
15.67
497.42
20.73
Tested bottom of hole and found junk


1615
Dec 5
Bit at rotary table
6.33
503.75
20.99
Change to Bowen fishing magnet


2358
Dec 5
Reentry 7
7.72
511.47
21.31
Quick reentry


0230
Dec 6
Start fishing
2.53
514.00
21.42
Work junk baskets and magnet 1 hr


0440
Dec 6
Clear seafloor
2.17
516.17
21.51
Quick reentry


1130
Dec 6
Bit at rotary table
6.83
523.00
21.79
Clean magnet. Bit 2: CC-7 SN BP-723


2130
Dec 6
Reentry 8
10.00
533.00
22.21
1-hr search for cone


0045
Dec 7
Work junk basket
3.25
536.25
22.34
Work junk basket before coring


0100
Dec 7
Begin coring bit 2
0.25
536.50
22.35
Clean hole!


0900
Dec 10
End coring
80.00
616.50
25.69
Hr = 49.58; cored = 129.9 m (158.0 m in basement)


1203
Dec 10
Work stuck pipe
3.05
619.55
25.81
Stuck when sinker bars pulled


1435
Dec 10
Clear seafloor
2.53
622.08
25.92



2040
Dec 10
Bit at rotary table
6.08
628.17
26.17
Bit 3: CC-7 SN BP-737


0410
Dec 11
Reentry 9
7.50
635.67
26.49



0845
Dec 11
Begin coring bit 3
4.58
640.25
26.68



2145
Dec 14
End coring
85.00
725.25
30.22
Hr = 62.9; cored = 88.0 m (244.0 m in basement)


2340
Dec 14
Clear seafloor
1.92
727.17
30.30



0655
Dec 15
Bit at rotary table
7.25
734.42
30.60
Bit 4: CC-9 SN BF-857, no junk basket


1435
Dec 15
Reentry 10
7.67
742.08
30.92
Quick reentry


1800
Dec 15
Begin coring bit 4
3.42
745.50
31.06



2200
Dec 18
End coring
76.00
821.50
34.23
Hr = 57.8; cored = 77.0 m (321.0 m in basement)


2355
Dec 18
Clear seafloor
1.92
823.42
34.31



0740
Dec 19
Bit at rotary table
7.75
831.17
34.63



1550
Dec 19
Reentry 11
8.17
839.33
34.97
Bit 5: CC-9 SN BF-738


1915
Dec 19
Begin coring bit 5
3.42
842.75
35.11
3 m soft fill


2000
Dec 22
End coring
72.75
915.50
38.15
Hr = 59.4; cored = 84.0 m (405.0 m basement)


0010
Dec 23
Clear seafloor
4.17
919.67
38.32



0625
Dec 23
Bit at rotary table
6.25
925.92
38.58
Bit 6: CC-9 SN BF-740


1540
Dec 23
Reentry 12
9.25
935.17
38.97
1 hr dt piperacker


1845
Dec 23
Begin coring Bit 6
3.08
938.25
39.09



1145
Dec 27
End coring
89.00
1027.25
42.80
Hr = 64.9; cored = 97.0 m (502.0 m basement)


1515
Dec 27
Clear seafloor
3.50
1030.75
42.95



2300
Dec 27
Bit at rotary table
7.75
1038.50
43.27



0622
Dec 28
Reentry 13
7.37
1045.87
43.58
Enter cone with logging BHA


0915
Dec 28
Rig-up for logging
2.88
1048.75
43.70
Recover VIT camera


1000
Dec 28
Rig-up first log
0.75
1049.50
43.73



1930
Dec 30
End logging
57.50
1107.00
46.13
BGR magnetometer (BGRM) did not work; two runs


2030
Dec 30
Rig-down from logging
1.00
1108.00
46.17
Triple combo, FMS, BGRM, UBI, WST


2100
Dec 30
Clear seafloor
0.50
1108.50
46.19



0325
Dec 31
Bit at rotary table
6.42
1114.92
46.45



0330
Dec 31
Underway to Balboa
0.08
1115.00
46.46
Beacon recovered after 45 days

Notes: GPS = Global Positioning System. EOP = end of pipe. BHA = bottom-hole assembly. TD = total depth. POOH = pull out of hole. WOW = waiting on weather. VIT = vibration isolated television. FMS = Formation MicroScanner, UBI = ultrasonic borehole imager, WST = well seismic tool.