SITE KIP-9B SITE
SUMMARY
Site:
KIP-9B
Track line 9B
Seismic for KIP-9B
Priority:
1
Position:
32°07.3´S, 97°00.4´E
Water
Depth: 1240 m
Sediment
Thickness: 160 m
Target
Drilling Depth: 360 mbsf
Approved
Maximum Penetration: 560 mbsf
Seismic
Coverage: 1986 single-channel seismic line Robert
Conrad 2708
Objectives:
The objectives of KIP-9B are to
- obtain
200 m of igneous basement to characterize petrography and
lava compositions,
- determine
basalt flow thicknesses,
- obtain
sedimentary record and determine sequence facies,
- determine
a minimum basement age using overlying sediment and
possible sediment interbeds,
- define
the ages of seismic sequence boundaries, and
- estimate
duration of possible subaerial and shallow-water
environments.
Drilling
Program: RCB
Logging
and Downhole Operations: Triple combo, FMS/DSI, WST, DLL/NGT
Nature
of Rock Anticipated: Calcareous ooze, basalt