LEG 193 - EASTERN MANUS BACK ARC BASIN (P479-Rev2)
OPERATIONS PLAN AND TIME ESTIMATE FOR PRIMARY SITES
Site | Location | Water | Projected Operations Plan | Transit | Drilling | Logging | Total |
No. | Lat/Long | Depth | (depths in mbsf) | (days) | (days) | (days) | On-site |
Guam | 013°20.0'N | Port call activities - Guam | |||||
159°57.789'E | |||||||
Transit 1147 nmi from Guam to PCM-2A @ 10.5 kt | 4.6 | ||||||
PCM-2A | 3°43.690'S | 1655m | Hole A: RCB/ADCB core to ~500 mbsf, | 14.4 | 1.4 | 15.8 | |
151°40.200'E | 1st/2nd bits RCB, then 3rd/4th bits ADCB | ||||||
Log w/triple combo, FMS-DSI, temp tool, and 2 ea fluid samples | |||||||
DP move 0.6 nmi from PCM-2A to PCM-3A @ 1.5 kt | 0.1 | ||||||
PCM-3A | 3°43.230'S | 1696m | Hole A: RCB/ADCB core to ~300 mbsf, | 8.6 | 1.2 | 9.8 | |
151°40.521'E | 1st bit RCB and 2nd bit ADCB | ||||||
Log w/triple combo, FMS-DSI, temp tool, and 2 ea fluid samples | |||||||
DP move from PCM-3A to PCM-1A @ 1.5 kt | 0.1 | ||||||
PCM-1A | 3°43.293'S | 1720m | Hole A: RCB/ADCB core to ~300 mbsf, | 8.6 | 1.2 | 9.8 | |
151°40.583'E | 1st bit RCB and 2nd bit ADCB | ||||||
Log w/triple combo, FMS-DSI, temp tool, and 2 ea fluid samples | |||||||
DP move from PCM-1A to PCM-3A @ 1.5 kt | 0.1 | ||||||
  | |||||||
PCM-3A | 3°43.230'S | 1696m | Hole B: LWD/RAB hole to ~100 mbsf | 2.6 | 2.6 | ||
(return to) | 151°40.521'E | ||||||
DP move from PCM-3A to PCM-2A @ 1.5 kt | 0.1 | ||||||
PCM-2A | 3°43.690'S | 1655m | Hole B: LWD/RAB hole to ~100 mbsf | 2.6 | 2.6 | ||
(return to) | 151°40.200'E | ||||||
DP move from PCM-2A to PCM-1A @ 1.5 kt | 0.1 | ||||||
  | |||||||
PCM-1A | 3°43.293'S | 1720m | Hole B: LWD/RAB hole to ~100 mbsf | 2.9 | 2.9 | ||
(return to) | 151°40.583'E | ||||||
Townsville | 019°07.8' S | Transit 1075 nmi from PCM-1A to Townsville @ 10.5 kt | 4.4 | ||||
146°28.8' E | |||||||
9.5 | 31.6 | 11.9 | 43.5 | ||||
Note: Total includes 5.0 day port call. | TOTAL DAYS: | 58.0 |
DATE: 25 April 2000
FILE: I:\ DATA \ DSD_INFO \ Leg193\193ProjB.xls