LEG 193 - EASTERN MANUS BACK ARC BASIN (P479-Rev2)
ALTERNATE SITES

Site Location Water Projected Operations Plan Transit Drilling Logging Total
No. Lat/Long Depth (depths in mbsf) (days) (days) (days) On-site
               
PCM-4A 3°44.445'S 2139m Hole A: RCB to 300 mbsf n/a 9.0 1.4 10.4
(4th priority 151°40.755'E   Log w/triple combo, FMS-DSI, and temp tool/fluid sampling        
site)              
               
PCM-5A 3°43.115'S 1647m Hole A: RCB to 700 mbsf. Drilling plan TBD based upon results n/a 20.4 1.6 22.0
(alternate to 151°41.084'E   at PCM-2A. Possible bare hole reentry or FFF or reentry cone        
PCM-1A)     Log w/triple combo, FMS-DSI, and temp tool/fluid sampling        
               
               
PCM-6A 3°43.433'S 1725m Hole A: RCB to 700 mbsf. Drilling plan TBD based upon results n/a 20.4 1.6 22.0
(alternate to 151°41.727'E   at PCM-2A. Possible bare hole reentry or FFF or reentry cone        
PCM-1A)     Log w/triple combo, FMS-DSI, and temp tool/fluid sampling        
               
               
PCM-7A 3°43.600'S 1700m Hole A: RCB to TBD mbsf. Drilling plan TBD based upon results n/a 8.6 1.2 9.8
(alternate to 151°40.325'E   at PCM-2A. Possible bare hole reentry or FFF or reentry cone        
PCM-3A)     Log w/triple combo, FMS-DSI, and temp tool/fluid sampling        
               
               
PCM-8A 3°43.790'S 1690m Hole A: RCB to 300 mbsf. Drilling plan TBD based upon results n/a 8.6 1.2 9.8
(alternate to 151°40.015'E   at PCM-2A. Possible bare hole reentry or FFF or reentry cone        
PCM-3A)     Log w/triple combo, FMS-DSI, and temp tool/fluid sampling        

DATE: 25 April 2000
FILE: I:\ DATA \ DSD_INFO \ Leg193\193ProjB.xls
BY: M. A. Storms