Operations PlanOption 2 | Site HE-1A Summary | Table of Contents
Leg 197 Operations Plan and Time Estimate | |||||||
Option 1 | |||||||
Site | Location | Water | Operations Description | Transit | Drilling | Logging | Total |
No. | Lat/Long | Depth | (days) | (days) | (days) | On-site | |
(mbrf) | |||||||
Yokohama | 35°16.80'N | Transit 1572 nmi from Yokohama, Japan to Site HE-1B @ 11.0 kt | 6.0 | ||||
139°23.40'E | |||||||
HE-1B | 52°53.00'N | 3200 | Drill ahead with a center bit to 800 mbsf. | 9.6 | 0.9 | 10.5 | |
164°35.00'E | RCB in sediment from 800 to 950 mbsf | ||||||
Wireline logs (Triple combo and FMS) | |||||||
Transit 167 nmi from Site HE-1B to Site HE-3B @ 11.0 kt | 0.6 | ||||||
HE-3B | 50°48.60'N | 2740 | Drill ahead through sediment with a center bit to 450 mbsf | 7.1 | 1.1 | 8.2 | |
167°33.00'E | RCB from 450 to 600 mbsf (150 m into basement) using FFF | ||||||
for one bit change | |||||||
Wireline logs (Triple combo, Mag Tool, and FMS) | |||||||
Transit 574 nmi from Site HE-3B to Site HE-4B @ 10.5 kt | 2.3 | ||||||
HE-4B | 41°29.00'N | 1300 | RCB to 190 mbsf (150 m into basement) | 4.8 | 0.5 | 5.3 | |
170°38.00'E | Wireline logs (Triple combo and FMS) | ||||||
Transit 200 nmi from Site HE-4B to Site HE-5C @ 10.5 kt | 0.8 | ||||||
HE-5C | 38°09.50'N | 1480 | RCB to 210 mbsf (150 m into basement) | 4.9 | 0.5 | 5.4 | |
170°50.00'E | Wireline logs (Triple combo and FMS) | ||||||
Transit 201 nmi from Site HE-5C to Site HE-6A @ 10.5 kt | 0.8 | ||||||
HE-6A | 34°58.94'N | 1331 | RCB to 230 mbsf (150 m into basement) | 4.8 | 0.5 | 5.3 | |
172°08.98'E | Wireline logs (Triple combo and FMS) | ||||||
Yokohama | 35°16.80'N | Transit 1640 nmi from Site HE-6A to Yokohama, Japan @ 10.0 kt | 6.8 | ||||
139°23.40'E | |||||||
TOTAL: | 17.3 | 31.2 | 3.5 | 34.7 | |||
TOTAL DAYS: | 52.0 |
Operations PlanOption 2 | Site HE-1A Summary | Table of Contents