Leg 197 Operations Plan and Time Estimate | |||||||
Option 2 | |||||||
Site | Location | Water | Operations Description | Transit | Drilling | Logging | Total |
No. | Lat/Long | Depth | (days) | (days) | (days) | On-site | |
(mbrf) | |||||||
Yokohama | 35°16.80'N | Transit 1552 nmi from Yokohama, Japan, to Site HE-3B @ 11.0 kt | 5.9 | ||||
139° 23.40' E | |||||||
HE-3B | 50° 48.60' N | 2740 | Drill ahead through sediment with a center bit to 450 mbsf | 7.6 | 1.3 | 8.9 | |
167° 33.00' E | RCB from 450 to 620 mbsf (170 m into basement) using | ||||||
FFF for one bit change | |||||||
Wireline logs (Triple combo, Mag Tool, and FMS) | |||||||
Transit 11 nmi from Site HE-3B to Site HE-3A @ 11.0 kt | 0.0 | ||||||
HE-3A | 50° 57.00' N | 2773 | Drill ahead through sediment with a center bit to 500 mbsf | 7.5 | 0.9 | 8.4 | |
167° 44.40' E | RCB from 500 to 670 mbsf (170 m into basement) using FFF | ||||||
for one bit change | |||||||
Wireline logs (Triple combo and FMS) | |||||||
Transit 580 nmi from Site HE-3A to Site HE-4B @ 10.5 kt | 2.3 | ||||||
HE-4B | 41° 29.00' N | 1300 | RCB to 220 mbsf (180 m into basement) | 5.4 | 0.6 | 6.0 | |
170° 38.00' E | Wireline logs (Triple combo and FMS) | ||||||
Transit 200 nmi from Site HE-4B to Site HE-5C @ 10.5 kt | 0.8 | ||||||
HE-5C | 38° 09.50' N | 1480 | RCB to 240 mbsf (180 m into basement) | 5.6 | 0.6 | 6.2 | |
170° 50.00' E | Wireline logs (Triple combo and FMS) | ||||||
Transit 201 nmi from Site HE-5C to Site HE-6A @ 10.5 kt | 0.8 | ||||||
HE-6A | 34° 58.94' N | 1331 | RCB to 260 mbsf (180 m into basement) | 5.4 | 0.6 | 6.0 | |
172° 08.98' E | Wireline logs (Triple combo and FMS) | ||||||
Yokohama | 35° 16.80' N | Transit 1640 nmi from Site HE-6A to Yokohama, Japan @ 10.0 kt | 6.8 | ||||
139° 23.40' E | |||||||
TOTAL: | 16.5 | 31.5 | 4.0 | 35.5 | |||
TOTAL DAYS: | 52.0 |