Table 1. Leg 201 Operations Plan and Time Estimate for Primary Sites

    Water     Total Total Total Total
Site Location Depth     Transit Drilling Logging On-site
No. (Lat/Long) (mbrf) Operations Description (hrs) (days) (days) (days) (days)
                 
San Diego 32.45°N, 117.10°W   In Port San Diego - Refuel/resupply/crew change 120.0        
                 
      Transit 1837 nmi from San Diego to EQP-2A @ 10.5 kt 175.0 7.3      
                 
EQP-2A 2°46.2'N 3791 Hole A: APC 120m/XCB to 318m, APCT, APCM, DVTP-P, PCS 70.6   2.9    
(ODP 851- 110°34.3'W   Hole B: TBD (est 36.9 hrs/1.5 days)          
Leg 138)     Hole C: APC 120m/XCB to 318m (10 hr to log w/triple combo) 79.5   2.9 0.4 6.2
                 
      Transit from EQP-2A to EQP-1A: 1243 nmi @ 10.5 kts 118.4 4.9      
                 
EQP-1A 3°5.7'S 3325 Hole A: APC 200m/XCB to 400m, APCT, APCM, DVTP-P, PCS 73.2   3.1    
(ODP 846- 90°49.1'W   Hole B: TBD (est 42.5 hrs/1.8 days)          
Leg 138) (methane expected)   Hole C: APC 200m/XCB to 400m (10 hr to log w/triple combo) 83.6   3.1 0.4 6.6
                 
      Transit from EQP-1A to PRU-3A: 697 nmi @ 10.5 kts 66.4 2.8      
                 
PRU-03A 8°59.5'S 437 Hole A: APC 50m/XCB to 160m, APCT, APCM, DVTP-P 35.0   1.4    
(ODP 684- 79°54.4'W   Hole B: TBD (est 13.4 hrs/0.6 days)          
Leg 112)     Hole C: APC 50m/XCB to 160m (no wireline logging) 31.6   1.3 0.0 2.7
                 
      Transit from PRU-03A to PRU-2A: 259 nmi @ 10.5 kts 24.7 1.0      
                 
PRU-02A 11°3.9'S 264 Hole A: APC 100m/XCB to 200m, APCT, APCM, DVTP-P 36.7   1.5    
(ODP 680- 78°4.7'W   Hole B: TBD (estimate: 14.8 hrs/0.6 days)          
Leg 112)     Hole C: APC 100m/XCB to 200m (7.5 hr to log w/triple combo) 44.8   1.6 0.3 3.4
                 
      Transit from PRU-2A to PRU-1A: 9 nmi @ 10.5 kts 0.9 0.1      
                 
PRU-01A 10°58.6'S 162 Hole A: APC 110m/XCB to 200m, APCT, APCM, DVTP-P 39.4   1.6    
(ODP 681- 77°57.5'W   Hole B: TBD (estimate: 18.7 hrs/0.8 days)          
Leg 112) (shallow gas ???)   Hole C: APC 110m/XCB to 200m (7.5 hr to log w/triple combo) 48.5   1.7 0.3 3.6
                 
      Transit from PRU-1A to PRU-4A: 156 nmi @ 10.5 kts 14.8 0.6      
                 
PRU-04A 9°6.8'S 5081 Hole A: APC 40m/XCB to 200m, APCT, APCM, DVTP-P, PCS 90.3   3.8    
(ODP 685- 80°35.0'W   Hole B: TBD (estimate: 55.7 hrs/2.3 days)          
Leg 112) (possible gas hydrates)   Hole C: APC 40m/XCB to 200m (11.0 hr to log w/triple combo) 104.1   3.8 0.5 8.1
                 
      Transit from PRU-4A to PRB-2A: 201 nmi @ 10.5 kts 19.2 0.8      
                 
PRB-02A 12°1.3'S 4838 Hole A: APC to 124m, APCT, APCM, DVTP-P 54.2   2.3    
(DSDP 321- 81°54.2'W   Hole B: TBD (estimate: 22.1 hrs/0.9 days)          
Leg 34)     Hole C: APC to 124m (no wireline logging) 49.4   2.1 0.0 4.4
                 
      Transit 1390 nmi from PRB-2A to Valparaiso @ 10.5 kt 131.7 5.5      
                 
Valparaiso 33.05°S, 71.4°W   End of Leg - In port Valparaiso, Chile 0.0        
                 
SUBTOTAL:   23.0 33.1 1.9 35.0
  ESTIMATED OPERATING DAYS (including 5.0 day port call):   63.0
Time Estimate File: leg201.dat         M. Storms 12-Jun-01