Table T2. Operations plan and time estimates for Leg 203.
| Site | Location & Depth | Operations Description | Transit (days) |
Drilling (days) |
Logging (days) |
On-site (days) |
| Balboa | 8.57°N, 79.33°W | Transit from Balboa to proposed Site OSN-2, ~1899 nmi @ 10.5 kt | 7.54 | |||
| OSN-2 | 5°17.566'N, 110°04.579'W | Hole A: Cased reentry hole for multidisciplinary observatory | ||||
| Water depth = 3860 m | 1. Geophysical survey and jet-in test. | 1.33 | 1.33 | |||
| 2. Set reentry cone and jet-in ~60 m of 20-in casing. | 1.41 | 1.41 | ||||
| 3. Drilling to ~140 mbsf with 18.5-in tricone bit and set 16-in casing to ~130 mbsf. | 3.12 | 3.12 | ||||
| 4. Drill out cement and casing shoe and RCB core in basement from 140 to 216 mbsf. | 2.33 | 2.33 | ||||
| 5. Wireline logging from 130 to 216 mbsf. | 1.77 | 1.77 | ||||
| 6. Drill 14.75-in hole from 130 to 216 mbsf and set 10.75-in casing to ~211 mbsf. | 4.21 | 5.98 | ||||
| Hole B: RCB coring and logging if time permits (see Table 3) | ||||||
| Prepare for transit. | 0.33 | 0.33 | ||||
| San Francisco | 44.6°N, 125.1°W | Transit from proposed Site OSN-2 to San Francisco, ~2486 nmi @ 10.5 kt | 9.87 | |||
| SUBTOTAL: | 17.4 | 12.7 | 1.8 | 16.3 | ||
| TOTAL REQUIRED OPERATING DAYS: | 31.9 | |||||