Table T3. Time estimates for secondary operations that may be conducted if extra time is available.
Site | Location & Depth | Operations Description | Transit (days) |
Drilling (days) |
Logging (days) |
On-site (days) |
PREFERRED OPTION | ||||||
OSN-2 | 5°17.566'N, 110°04.579'W | Hole B: RCB coring and logging if time permits | ||||
Water depth = 3860 m | 1. RCB drill to ~80 mbsf and core from 80 to 140 mbsf. | 1.15 | 1.15 | |||
2. Release bit and wireline log with triple combo and FMS/sonic toolstrings. | 1.59 | 1.59 | ||||
Subtotal | 0.00 | 1.15 | 1.59 | 2.74 | ||
OTHER SECONDARY OPTIONS | ||||||
5°17.566'N, 110°04.579'W | Hole A: After completing casing, run cement bond | |||||
OSN-2 | Water depth = 3860 m | Log in 10.75-in casing from 140 to 211 mbsf. | 1.30 | 1.30 | ||
5°17.566'N, 110°04.579'W | ||||||
OSN-2 | Water depth = 3860 m | Holes C and D: Double APC coring to 116 mbsf | 2.48 | 2.48 | ||
Site Summary | Table of Contents