Table 1. Operations plan and time estimate for Leg 205 primary sites.

Site
No.
Location
Lat./Long.
Water
Depth
Operations Description Transit
(days)
On-Site
(days)
 
San Diego 32° 27' N   Transit 2336 nmi San Diego to Site 1039R-A 8.8  
117° 6' W
           
1039R-A
Basement
9° 38.9' N 4375 Set reentry cone w/ 60 m 16" casing   19.2
86° 11.4' W m Drill 60 - 370 mbsf, RCB core 370 - 620 mbsf (100 m basement)
      Log: Triple Combo, FMS-Sonic, 370 - 620 mbsf
      Open hole to 14-3/4" 60 - 535 mbsf for 10-3/4" casing
      Set 10-3/4" casing to 530 mbsf
      Drill out casing shoe, clean rat hole to 620 mbsf
      Set Osmo screen @ 550 mbsf on 4-1/2" csg w/ pkr @ 540 mbsf
      Deploy OsmoSampler(s) on wireline
      Deploy ROV / Submersible platform
           
Transit     Transit 1.1 nmi Site 1039R-A to Site 1040R-B 0.1  
           
1040R-B
Decollement
9° 39.7' N 4125 Set reentry cone w/ 60 m 16" casing   9.4
86° 10.7' W m Drill 60 - 300 mbsf, RCB core 300 - 365 mbsf
      Open hole to 14-3/4" 60 - 337 mbsf for 10-3/4" casing
      Set 10-3/4" casing to 332 mbsf
      Drill out casing shoe, clean rat hole to 365 mbsf
      Set Osmo screen @ 357 mbsf on 4-1/2" csg w/ pkr @ 347 mbsf
      Deploy OsmoSampler on wireline
      Deploy ROV / Submersible platform
           
Transit     Transit 0.3 nmi Site 1040R-B to Site 1040R-C 0.1  
           
1040R-C
Decollement
9° 39.5' N 4250 Set reentry cone w/ 60 m 16" casing   8.8
86° 10.9' W m Drill 60 - 220 mbsf, RCB core 220 - 279 mbsf
      Open hole to 14-3/4" 60 - 255 mbsf for 10-3/4" casing
      Set 10-3/4" casing to 250 mbsf
      Drill out casing shoe, clean rat hole to 279 mbsf
      Set Osmo screen @ 270 mbsf on 4-1/2" csg w/ pkr @ 260 mbsf
      Deploy OsmoSampler on wireline
      Deploy ROV / Submersible platform
           
Transit     Transit 0.4 nmi Site 1040R-C to Site 1040R-A 0.1  
           
1040R-A
Under Thrust
9° 39.8' N 4100 Set reentry cone w/ 60 m 16" casing   7.4
86° 10.7' W m Drill 14-3/4" 60 - 385 mbsf for 10-3/4" casing
      Set 10-3/4" casing to 380 mbsf
      Drill out casing shoe, drill 9-7/8" 385 to 410 mbsf
      Set Osmo screen @ 400 mbsf on 4-1/2" csg w/ pkr @ 390 mbsf
      Deploy OsmoSampler on wireline
      Deploy ROV / Submersible platform
      Secure for sea voyage
           
Balboa 8° 34.2' N   Transit 510 nmi Site 1040R-A to Balboa, Panama 1.9  
79° 19.8' W
           
Primary Site Transit and On-Site Time Sub Totals: 11.2 44.8
           
LEG 205 PRIMARY SITE OPERATIONAL DAYS TOTAL: 56.0