SCENARIO A (double casing)
|
|
|
|
Balboa
|
8.57°N, 79.33°W
|
Transit from Balboa to GUATB-03C, 833 nmi @ 10.5 kt
|
3.3
|
|
|
|
GUATB-03C
|
6°44.19'N, 91°56.06'W
|
Hole A: APC/XCB to 240 m sediment + 5 m basement, jet-in test
|
|
2.9
|
|
|
water depth = 3655 m
|
Hole B: Drill to 230 m, RCB to bit destruction (~360 mbsf),
|
|
4.6
|
|
|
|
Log (triple combo-MGT, FMS/sonic, and BGR magnetometer)
|
|
|
1.2
|
|
|
Hole C: Set reentry cone, jet-in 80 m of 20-in casing
|
|
1.6
|
|
|
|
Drill 21.5-in-diameter hole to 270 mbsf with bi-center bit
|
|
4.8
|
|
|
|
Set 260 m of 16-in casing (20 m into basement) and cement
|
|
2.7
|
|
|
|
Drill through cement shoe, RCB core thru basalt to ~1050 mbsf
|
|
27.5
|
|
|
|
Wireline log (triple combo-MGT, FMS/sonic, and WST-3)
|
|
|
1.9
|
|
|
Wireline log with the BGR borehole magnetometer
|
|
|
0.3
|
|
|
Wireline log with the UBI
|
|
|
0.4
|
|
|
Pipe trip to the surface and secure for transit
|
|
0.5
|
|
|
Balboa
|
8.57°N, 79.33°W
|
Transit from GUATB-03C to Balboa, 833 nmi @ 10.5 kt
|
3.3
|
|
|
|
|
|
6.6
|
44.6
|
3.8
|
|
|
|
55.0
|
|
|
|
|
|
SCENARIO B (triple casing)
|
|
|
|
Balboa
|
8.57°N, 79.33°W
|
Transit from Balboa to GUATB-03C, 833 nmi @ 10.5 kt
|
3.3
|
|
|
|
GUATB-03C
|
6°44.19'N, 91°56.06'W
|
Hole A: APC/XCB to 240 m sediment + 5 m basement, jet-in test
|
|
2.9
|
|
|
water depth = 3655 m
|
Hole B: Drill to 230 m, RCB to bit destruction (~360 mbsf),
|
|
4.6
|
|
|
|
Log (triple combo-MGT, FMS/sonic, and BGR magnetometer)
|
|
|
1.2
|
|
|
Hole C: Set reentry cone, jet-in 80 m of 20-in casing
|
|
1.6
|
|
|
|
Drill 21.5-in-diameter hole to 360 mbsf with bi-center bit (2 bits)
|
|
10.0
|
|
|
|
Set 350 m of 16-in casing (110 m into basement) and cement
|
|
2.7
|
|
|
|
RCB core from 360 to 490 mbsf, or to whatever depth required
|
|
4.5
|
|
|
|
Log (triple combo-MGT, FMS/sonic, and BGR magnetometer)
|
|
|
1.4
|
|
|
Open hole 360490 mbsf to 18.5-in with bi-center bit (2 bits)
|
|
4.0
|
|
|
|
Set 480 m of 13 3/8-in casing (240 m into basement)
|
|
2.4
|
|
|
|
Drill through cement shoe, RCB core thru basalt to ~770 mbsf
|
|
10.5
|
|
|
|
Wireline log (triple combo-MGT, FMS/sonic, and WST-3)
|
|
|
1.5
|
|
|
Wireline log with the BGR borehole magnetometer
|
|
|
0.3
|
|
|
Wireline log with the UBI
|
|
|
0.3
|
|
|
Pipe trip to the surface and secure for transit
|
|
0.5
|
|
|
Balboa
|
8.57°N, 79.33°W
|
Transit from GUATB-03C to Balboa, 833 nmi @ 10.5 kt
|
3.3
|
|
|
|
|
|
6.6
|
43.7
|
4.7
|
|
|
|
55.0
|
|
|
|
|
|
|
|
|
|
GUATB-03B
|
6°43.64'N, 91°56.66'W
|
The operations plan is the same as given above for primary site.
|
|
|
|
|
water depth = 3650 m
|
|
|
|
|
|
GUATB-03A
|
6°40.64'N, 91°55.94'W
|
The operations plan is the same as given above for primary site.
|
|
|
|
|
water depth = 3621 m
|
|
|
|
|
|
GUATB-01A
|
7°55.50'N, 90°32.64'W
|
The operations plan is the same as given above for primary site.
|
|
|
|
|
water depth = 3454 m
|
|
|
|
|
|