OPERATIONS SYNOPSIS
Hole 1177A
The PDR indicated a drilling depth of 4851.4 mbrf. A standard RCB BHA
was made up and run down to the seafloor. At 1500 hr on 30 June, the driller
perceived the seafloor by a reduction in drill string weight at 4844.3 mbsl
(4856 mbrf). Hole 1177A was then spudded and drilled to 300.2 mbsf
(5156.2 mbrf). Davis-Villinger temperature probe measurements were taken
at 50.5 mbsf (4906.5 mbrf) and 120 mbsf (4976.0 mbrf) but did not obtain
good data. Hole 1177A was then cored from 300.2 to 833.9 mbsf (Cores 1R
to 56R) and recovered 282.74 m (53%).
Coring was stopped after basalt was recovered in Core 56R. The bit was
then tripped out of the hole. Once the bit had cleared the seafloor, the drill
line was slipped and cut. The seafloor positioning beacon was released and
recovered at 0910 hr on 5 July. The bit cleared the rig floor at 1730 hr on 5
July, ending operations at Site 1177, and the transit to Site 1178 began at
1930 hr on 5 July.
Transit from Site 1177 to Site ENT-10A
Once the bit arrived on deck, the transit to Site ENT-10A began at 1930
hr on 5 July. Typhoon Kirogi was approaching our location from the south and
was predicted to pass close to the drill site. Although the weather in the
vicinity of the vessel was good, a heavy swell was coming out of the south,
causing excessive vessel pitch and roll. Because of the deep water depth at
Site ENT-10A (~4554 mbsl) we decided not to deploy the drill string and to
suspend operations until the weather would allow safe operations. While the
vessel was on standby, 20 stands of 5-in drill pipe were removed from the
riser hold, made up, and placed in the middle bay of the pipe racker. The
leaking AHC hydraulic umbilical was removed and placed on pallets on main
deck, and the coaxial cable was removed from the VIT winch in preparation
for installation of the new cable during the Yokohama port call after the leg.
At 1045 hr on 7 July, we decided to move the vessel out of the path of
typhoon Kirogi and maintain at least a 250-nmi distance from it. The vessel
was moved ~98 nmi to the west and then looped around behind the typhoon.
Because of the loss in operations time as a result of the typhoon, all of the
Site ENT-10A objectives could not be accomplished. Therefore, we decided to
core at alternate Site ENT-09A (1178) instead.