TABLE 1. SITE OPERATIONS SUMMARY (Priority 1)
Site (Lat/Long) Line/Shot Water Penetration Operations Time
Location Depth Sediment (m)/ (days)
(m) Basement (m)
Transit 2.7
HT-1A 47°55.56'N 95-15/170 2600 85/1 APC/XCB 0.9
128°50.02'W
Transit 0.1
HT-2A 47°55.04' 95-15/300 2608 195/1 APC/XCB 1.3
128°47.52'
Transit 0.1
HT-4A 47°53.25' 95-15/750 2637 105/40 RCB/CORK 9.9
128°38.90'
Transit 0.2
PP-1A 47°46.52' 95-27/420 2683 415/1 APC/XCB 4.0
127°43.52'
Transit 0.1
PP-3A 47°46.79' 95-27/350 2681 185/1 APC/XCB 1.4
127°44.85'
Transit 0.1
PP-4A 47°45.41' 95-26/430 2683 535/40 RCB/CORK 13.6
127°43.85'
Transit 0.1
PP-5A 47°45.76' 95-26/340 2679 220/40 RCB/CORK 10.4
127°45.55'
Transit 0.2
HT-3A 47°54.52' 95-15/430 2637 140/40 RCB/CORK 10.1
128°45.00'
Transit to Victoria, B.C. 0.9
Total Days 56.1
Note: These holes are listed according to the planned order of drilling.