Site WP-1B Summary | Table of Contents

Operations Plan and Time Estimate
               
Site Location Water Operations Description Transit Drilling Logging Total
No.   Depth         On-site
  (Lat/Long) (mbrf) (mbsf) (days) (days) (days) (days)
               
Guam 13.27° N, 144.38° E   Transit f/Apra Harbor, Guam to WP-1B, ~664 nmi @ 10.5 kt [62.2 hr] 2.60      
      (Note: Clocks retarded 1 hour during transit)        
               
WP-1B 19°17.85'N 5658 Hole A: APC/XCB to ~380 mbsf (basement contact) [101.0 hrs]   4.2   26.0
  135°5.95'E   plug hole with cement then, after clearing sea floor,        
      conduct jet-in test for Hole C reentry cone installation        
      APC Core orientation, ~5 ea Adara temperature measurements        
               
      Hole B: Drill w/RCB c'bit to ~360 mbsf [120.2]   5.0 1.6  
      Core w/RCB to ~470 mbsf, release bit w/MBR        
      Wireline logging to include: rig-up, triple combo, FMS-sonic        
      (2-passes in basement), DLL, UBI, and rig-down [38.0 hrs]        
               
      Hole C: Set reentry cone, jet-in 60m 16" casing [365.5 hrs]   15.2    
      Drill to ~425 mbsf w/14-3/4" tricone bit        
      Set and cement ~410 m of 10-3/4" 54 lb/ft casing        
      Drill ahead to ~470 mbsf w/9-7/8" tricone bit        
      Deploy/cement seismometer instrument pkg @ ~460 mbsf        
      Deploy and release from battery platform        
               
      Hole D: Should operations in holes A thru C be completed ahead of   TBD    
      schedule, there is interest in drilling a second APC/XCB(?)        
      hole with any remaining time.        
               
               
      Note: At the time of this writing, the end port in Chinese Taipai was        
      still under evaluation. Keelung has been requested as the end port        
      for PR purposes. This is currently under review. This time estimate        
      and operating plan assumes Keelung as the end port, however        
      the initial port, Kao-hsuing is also shown for information only.        
               
Kao-hsiung 22.36°N, 120.17°E   Transit f/ WP-1B to Kao-hsiung, Taiwan, ~876 nmi @ 10.2 kt [84.9 hrs] (3.54)      
or Keelung 25.09°N, 121.44°E   Transit f/ WP-1B to Keelung, Taiwan, ~826 nmi @ 10.2 kt [80.0 hrs] 3.33      
(Port for Taipei)     (Note: Clocks retarded 1 hour during transit)        
               
      SUBTOTAL: 5.9 24.5 1.6 26.0
      TOTAL OPERATING DAYS (Including 5 day port call): 37.0